BLD05-00631
| FIRE-Conference | 5/9/2006 | 5/9/2006 | 5/10/2006 11:38:19 AM | P | DONE |
|
|
I spoke to Lance, who is the warehouse manager, about what needs to be done to get the updated racking plans resubmitted to the city for approval so that I can do my inspection. I suggested that he contact Bill Alexander to see if it could be a plan modification or a totally new resubmittal.
|
BLD05-02834
| FIRE-Conference | 5/9/2006 | 5/9/2006 | 5/9/2006 4:04:05 PM | P | DONE |
|
|
I contacted Laten about getting this permit finaled. He stated that he believed everything was done except for one door and that he would follow up on it.
|
BLD05-02812
| FIRE-Final Inspection | 5/9/2006 | 5/9/2006 | 5/9/2006 3:58:30 PM | P | PASS |
|
|
Life safety finaled. I pointed out the maximum storage heights and other items to the general contractor. Warehouse was empty during inspection.
|
FIR06-00041
| INSP-Final Inspection | 5/9/2006 | 5/9/2006 | 5/9/2006 3:45:26 PM | P | FAIL |
|
|
Inspection was not for a final but was for an underground hydro test which passed. I had sam measure the amount of leakage which was about 12oz. 15oz was allowed.
|
FIR06-00068
| INSP-Sprinkler Rough-in | 5/9/2006 | 5/9/2006 | 5/9/2006 2:11:54 PM | P | PART |
|
|
Sprinkler rough-in passed for all piping installed south of column line 5. See approved plans for location that two heads need to be added. The spiral freezer is being relocated and has not been piped yet.
|
FIR06-00079
| INSP-Final Inspection | 5/8/2006 | 5/9/2006 | 5/9/2006 12:32:18 PM | A | CANC |
|
|
Scheduled by a contractor via Hello! on 5/8/2006 at 1:16:45 PM. Contact: ###-####.
|
BLD06-00430
| FIRE-Final Inspection | 5/9/2006 | 5/9/2006 | 5/9/2006 11:42:20 AM | P | PASS |
|
|
Life safety finaled
|
FIR06-00221
| INSP-Final Inspection | 5/8/2006 | 5/9/2006 | 5/9/2006 11:40:38 AM | A | PASS |
|
|
Permit finaled
|
BLD06-00573
| FIRE-Final Inspection | 5/8/2006 | 5/9/2006 | 5/9/2006 10:51:52 AM | A | FAIL |
|
|
Provide automatic flush bolts in the inactive leafes of the tenant separation doors
|
MIS06-00024
| FIR-Final | 5/8/2006 | 5/9/2006 | 5/9/2006 9:31:33 AM | A | PASS |
|
|
Life safety finaled. Structural inspector approved the use of the second exit out the front of the store for the secondary exit. This door has a crash bar and exit sign/emergency light.
|
BLD05-03484
| FIRE-Final Inspection | 5/8/2006 | 5/9/2006 | 5/8/2006 3:22:02 PM | A | FAIL |
|
|
Provide sensors as per approval notes
|
BLD06-00667
| FIRE-Final Inspection | 5/8/2006 | 5/9/2006 | 5/8/2006 2:14:28 PM | A | PASS |
|
|
Life safety finaled
|