Inspections for the day of: Tuesday, May 9, 2017.
Number of inspections: 6
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR17-00080 INSP-Sprinkler Rough-in5/9/20175/9/20175/9/2017 11:35:53 AMPPASS
The remaining tenting is complete for the north half of the building and the piping can be covered. The new canopy at the south end of the building still needs inspected when built.
FIR17-00115 INSP-Final Inspection5/8/20175/9/20175/9/2017 10:34:17 AMAPASS
Rough-in passed for the remaining sprinkler piping. Piping can be covered.
FIR17-00002 INSP-Sprinkler Rough-in/Hydro5/8/20175/9/20175/9/2017 9:22:20 AMACANC
Cancel per John Beazer due to leak found after start of test
FIR17-00088 INSP-Sprinkler Rough-in5/8/20175/9/20175/9/2017 8:51:21 AMAPASS
Rough-in passed piping can be covered.
BLD17-00392 FIRE-Final Inspection5/8/20175/9/20175/9/2017 8:50:48 AMAFAIL
Need project related fire sprinkler permit called in, need fire review comments, need verification that the smoke evac engineering is not required. Burt Phone #: ###-####
BLD17-01215 FIRE-Final Inspection5/8/20175/9/20175/8/2017 2:58:40 PMAPASS
life safety passed