FIR10-00038
| FIR-Aging Inspection | 6/1/2010 | 6/1/2010 | 6/2/2010 5:41:25 PM | | DONE |
|
|
Work in progress, site construction underway.
|
FIR06-00362
| FIR-Aging Inspection | 6/1/2010 | 6/1/2010 | 6/2/2010 5:06:52 PM | | DONE |
|
|
Scheduled for final.
|
FIR10-00103
| INSP-Conference | 6/1/2010 | 6/1/2010 | 6/1/2010 4:59:26 PM | P | DONE |
|
|
Regarding next site inspection schedule.
|
FIR10-00219
| INSP-Final Inspection | 6/1/2010 | 6/1/2010 | 6/1/2010 4:52:22 PM | P | PASS |
|
|
Scope of permit work completed satisfactory, inspection passed, permit finaled.
|
BLD08-00378
| FIRE-Final Inspection | 6/1/2010 | 6/1/2010 | 6/1/2010 4:49:32 PM | P | PASS |
|
|
Items on previous correction notice field verified for completion, fire life safety passed.
|
BLD08-01293
| FIRE-Final Inspection | 5/28/2010 | 6/1/2010 | 6/1/2010 4:48:13 PM | A | NR |
|
|
Intended by contractor for FIR08-00378- Phase II work per this permit scope is not complete.
|