FIR14-00604
| INSP-Sprinkler Rough-in | 6/1/2015 | 6/1/2015 | 6/1/2015 7:22:26 PM | P | CANC |
|
|
24 hour air test of dry pipe valve - 40 psi @ 1330 hrs.
|
FIR14-00735
| INSP-Sprinkler Rough-in | 6/1/2015 | 6/1/2015 | 6/1/2015 7:21:01 PM | P | PART |
|
|
24 hour air test - 40 psi at 1330 hrs.
|
FIR14-00792
| INSP-Sprinkler Rough-in/Hydro | 6/1/2015 | 6/1/2015 | 6/1/2015 2:20:39 PM | P | PART |
|
|
Hydrotest (partial) of Bldg H basement and first floor portions of the system needed for TCO of Bldgs A-D Phase 1 TCO. 200psi @ 2 hours - PASSED
|
FIR14-00068
| INSP-Final Inspection | 5/29/2015 | 6/1/2015 | 6/1/2015 2:14:05 PM | P | CANC |
|
|
Final signoff on FSUG cannot be granted until fire alarm system interface components, including tampers and waterflows, can be completed.
|
FIR14-00069
| INSP-Final Inspection | 5/29/2015 | 6/1/2015 | 6/1/2015 2:13:05 PM | P | CANC |
|
|
Final signoff on FSUG cannot be granted until fire alarm system interface components, including tampers and waterflows, can be completed.
|
FIR14-00070
| INSP-Final Inspection | 5/29/2015 | 6/1/2015 | 6/1/2015 2:11:48 PM | P | CANC |
|
|
Final signoff on FSUG cannot be granted until fire alarm system interface components, including tampers and waterflows, can be completed.
|
FIR14-00071
| INSP-Final Inspection | 5/29/2015 | 6/1/2015 | 6/1/2015 2:10:54 PM | P | CANC |
|
|
Final signoff on FSUG cannot be granted until fire alarm system interface components, including tampers and waterflows, can be completed.
|
FIR14-00069
| INSP-Sprinkler Rough-in/Hydro | 5/29/2015 | 6/1/2015 | 5/29/2015 1:38:20 PM | P | CANC |
|
|
Please call Leroy 30 mins prioor Phone #: ###-#### >> Inspection requested via web by Jacci Hunt Inspection cancelled from web by: Jacci Hunt
|