FIR15-00385
| INSP-Final Inspection | 5/29/2015 | 6/1/2015 | 6/1/2015 3:56:29 PM | P | CANC |
|
|
Life safety passed per this scope of work, End of line volatge 20.3
|
BLD15-01503
| FIRE-Conference | 6/1/2015 | 6/1/2015 | 6/1/2015 3:54:56 PM | P | DONE |
|
|
Consulted wih general contractor, areas throughtout the scope of work have issues with the fire sprinkler system. Heads are to close together (Less than 6ft) where a wall was removed, new cubicle office area, south side of tenant space. Heads in the new conference room are 10ft 6in off of the wall, south side of tenant space, heads are overspaced. Heads in the new cubicle office are are over 15ft apart, south side of tenant space, heads are overspaced. Calculations will need to be verified for square footage per head, check to see if fire sprinkler system can sustain 225 square feet per head based on light hazard application.
|
BLD14-03116
| FIRE-Final Inspection | 5/29/2015 | 6/1/2015 | 6/1/2015 3:19:50 PM | A | PART |
|
|
Contractor is working the project in phases. Second floor has not been started, but second floor work is on the same permit number, inspection will need to be performed on second floor at a later date. First floor inspected, life safety passed.
|
FIR14-00755
| INSP-Sprinkler Rough-in/Hydro | 5/29/2015 | 6/1/2015 | 6/1/2015 11:15:39 AM | A | PASS |
|
|
Overhead fire sprinkler piping/tenting approved for cover, hydrostatic test still needs completed
|
BLD15-01450
| FIRE-Final Inspection | 5/29/2015 | 6/1/2015 | 6/1/2015 11:11:31 AM | A | CANC |
|
|
Instructed onsite point of contact, Dennis, that an inspection for FIR15-00380 would need to be completed before I could perform the life safety inspection. Contractor is going to reshedule.
|