Inspections for the day of: Thursday, June 1, 2017.
Number of inspections: 21
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorJim Page
TitleFIRE INSPECTOR
Phone #208-914-5431
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR16-00267 INSP-Sprinkler Rough-in6/1/20176/1/20176/1/2017 3:18:45 PMPPART
Rough to cover inspection for overhead fire sprinkler piping on level 7 A wing (east wing) complete, approved for cover.
BLD16-03241 FIRE-Final Inspection5/31/20176/1/20176/1/2017 2:04:15 PMAPASS
Final fire sprinkler inspection complete, final fire alarm inspection complete (fire alarm permit, FIR17-00143, is not attached in project related cases), fire extinguishers are in place with current inspection tags, thumbturn locks on south entrance doors will be changed to double-key deadbolts before final BLD inspection. Final life fire safety inspection passed/complete.
FIR16-00088 INSP-Sprinkler Rough-in/Hydro6/1/20176/1/20176/1/2017 1:50:19 PMPPASS
Hydrostatic test complete for entire building.
BLD16-03558 FIRE-Final Inspection6/1/20176/1/20176/1/2017 11:47:32 AMPPASS
Fire sprinkler inspection complete, fire alarm inspection complete, fire extinguishers are in place with current inspection tags. Final life fire safety for area of work passed/complete
FIR16-00664 INSP-Final Inspection5/31/20176/1/20176/1/2017 11:34:48 AMACANC
Project not ready for inspection, inspection request rescheduled for 02JUNE2017
FIR17-00117 INSP-Final Inspection5/31/20176/1/20176/1/2017 11:30:20 AMAPASS
Final fire alarm inspection passed/complete
FIR16-00675 INSP-Sprinkler Rough-in6/1/20176/1/20176/1/2017 10:44:45 AMPPASS
Rough to cover inspection for underground supply complete
FIR16-00699 INSP-Sprinkler Rough-in6/1/20176/1/20176/1/2017 10:42:17 AMPPASS
Rough to cover inspection for underground supply complete
FIR16-00697 INSP-Sprinkler Rough-in6/1/20176/1/20176/1/2017 10:39:20 AMPPASS
Rough to cover inspection for underground supply complete
FIR16-00674 INSP-Sprinkler Rough-in6/1/20176/1/20176/1/2017 10:33:41 AMPPASS
Rough to cover inspection for underground was completed on 26JAN2017, main line flush was completed on 19APR2017. Notes were recorded under FIR16-00770
FIR16-00669 INSP-Sprinkler Rough-in6/1/20176/1/20176/1/2017 10:28:54 AMPPASS
Rough to cover inspection for underground complete (07DEC2016) as well as main line flush was complete (10MAY2017). Notes were recorded under FIR16-00743.
FIR16-00667 INSP-Sprinkler Rough-in/Hydro6/1/20176/1/20176/1/2017 10:24:39 AMPPASS
Notes for fire sprinkler inspections were recorded under FIR16-00741, rough to cover inspection has been completed for underground, overhead fire sprinkler piping/tenting, main line flush is complete, overhead fire sprinkler piping hydrostatic test complete.
FIR17-00097 INSP-Final Inspection6/1/20176/1/20176/1/2017 10:21:46 AMPPASS
Final fire sprinkler inspection passed/complete
BLD17-00195 FIRE-Final Inspection5/31/20176/1/20176/1/2017 10:13:01 AMAPASS
Fire sprinkler inspection complete (FIR17-00168 is not attached in project related cases), no fire alarm modifications (building does have a knox box installed), fire extinguisher is in place with a current inspection tag. Final life fire safety inspection passed/complete.
FIR17-00143 INSP-Final Inspection5/31/20176/1/20176/1/2017 9:52:19 AMAPASS
Final fire alarm inspection passed/complete
FIR16-00607 INSP-Supply line flush5/31/20176/1/20176/1/2017 8:55:55 AMACANC
Cancelled per point of contact, Paul Phone #: ###-####, will be rescheduled.
FIR16-00606 INSP-Supply line flush5/31/20176/1/20176/1/2017 8:55:28 AMACANC
Cancelled per point of contact, Paul Phone #: ###-####, will be rescheduled.
FIR17-00120 INSP-Final Inspection6/1/20176/1/20176/1/2017 8:52:39 AMPPASS
Final underground inspection passed/complete
FIR16-00674 INSP-Sprinkler Rough-in/Hydro5/31/20176/1/20176/1/2017 8:51:39 AMAPASS
Rough to cover inspection complete for overhead fire sprinkler piping/tenting complete, approved for cover. Hydrostatic test for overhead fire sprinkler piping complete.
FIR16-00774 INSP-Sprinkler Rough-in5/31/20176/1/20176/1/2017 8:16:38 AMAPASS
Insulation will be installed over the top of the tenting in the garages as well as heaters installed in the garages to turn them into conditioned spaces, all overhead fire sprinkler piping approved for cover.
FIR16-00755 INSP-Sprinkler Rough-in5/31/20176/1/20176/1/2017 8:16:07 AMAPASS
Insulation will be installed over the top of the tenting in the garages as well as heaters installed in the garages to turn them into conditioned spaces, all overhead fire sprinkler piping approved for cover.