BLD16-01323
| FIRE-Final Inspection | 6/9/2016 | 6/10/2016 | 6/10/2016 1:55:27 PM | P | PART |
|
|
Life fire safety inspection passed/complete for level 4, this is the last floor for inspection with this permit. Fire panel was still showing troubles with the alarm system at time of inspection, life fire safety inspection for this permit cannot be finaled until fire panel reads system is normal.
|
FIR15-00588
| INSP-Sprinkler Rough-in | 6/9/2016 | 6/10/2016 | 6/10/2016 10:28:21 AM | A | PART |
|
|
Rough in inspection for attic system complete, attic system approved for cover.
|
BLD15-04191
| FIRE-Final Inspection | 6/9/2016 | 6/10/2016 | 6/10/2016 9:54:19 AM | A | PART |
|
|
Fire sprinkler inspection complete for basement level, fire alarm inspection complete for basement level, fire extinguishers are in place with current inspection tags for basement level, will verify loading dock mag lock integration to fire alarm system at later date. Final life fire safety inspection for basement level complete excluding mag lock operation and elevator smoke curtians operation.
|
FIR16-00118
| INSP-Final Inspection | 6/8/2016 | 6/10/2016 | 6/10/2016 9:41:04 AM | A | PASS |
|
|
Final fire sprinkler inspection for level 2 complete.
|
FIR16-00258
| INSP-Final Inspection | 6/8/2016 | 6/10/2016 | 6/10/2016 9:39:17 AM | A | PASS |
|
|
Final inspection for basement wet system and loading dock dry system complete.
|
FIR16-00097
| INSP-Final Inspection | 6/8/2016 | 6/10/2016 | 6/10/2016 9:35:50 AM | A | PART |
|
|
Alarm inspection for audio visuals complete for level 3, level 2 and basement level. Final items to test/inspect, level one A/V's, smoke evacuation system for all levels, elevator smoke curtians, elevator recall and elevator shunt
|
FIR15-00776
| INSP-Final Inspection | 6/10/2016 | 6/10/2016 | 6/10/2016 8:26:32 AM | A | PASS |
|
|
Final underground inspection passed/complete
|
FIR16-00325
| INSP-Final Inspection | 6/9/2016 | 6/10/2016 | 6/9/2016 2:54:06 PM | A | PASS |
|
|
Inspection request for fire alarm final was completed on June 8th, inspection was requested as a rough in and not a final inspection. Final fire alarm inspection passed/complete.
|