BLD18-04125
| BLD-Framing/Rough-in | 6/10/2019 | 6/10/2019 | 6/10/2019 5:00:05 PM | P | PASS |
|
|
No framing... Second floor shear only...
|
BLD19-00514
| BLD-Other | 6/10/2019 | 6/10/2019 | 6/10/2019 4:59:17 PM | P | PASS |
|
|
Soffit- OK to cover...
|
BLD18-01375
| BLD-Conference | 6/10/2019 | 6/10/2019 | 6/10/2019 4:58:58 PM | P | DONE |
|
|
Firewall...
|
BLD18-01374
| BLD-Conference | 6/10/2019 | 6/10/2019 | 6/10/2019 4:58:39 PM | P | DONE |
|
|
Firewall...
|
BLD18-01370
| BLD-Conference | 6/10/2019 | 6/10/2019 | 6/10/2019 4:58:25 PM | P | DONE |
|
|
Firewall
|
BLD18-01706
| BLD-Wall Bracing | 6/10/2019 | 6/10/2019 | 6/10/2019 4:57:18 PM | P | PASS |
|
|
Gillermo Phone #: ###-####
|
BLD18-01705
| BLD-Wall Bracing | 6/10/2019 | 6/10/2019 | 6/10/2019 4:57:06 PM | P | PASS |
|
|
Gillermo Phone #: ###-####
|
BLD18-01704
| BLD-Wall Bracing | 6/10/2019 | 6/10/2019 | 6/10/2019 4:56:52 PM | P | PASS |
|
|
Gillermo Phone #: ###-####
|
BLD18-01702
| BLD-Wall Bracing | 6/10/2019 | 6/10/2019 | 6/10/2019 4:56:44 PM | P | PASS |
|
|
Gillermo Phone #: ###-####
|
BLD18-01491
| BLD-Framing/Rough-in | 6/7/2019 | 6/10/2019 | 6/10/2019 12:50:01 PM | A | DEFR |
|
|
Approved plans are in the riser room Phone #: ###-#### Inspection requested via web by Andy Eells
|
BLD19-00834
| BLD-Final | 6/7/2019 | 6/10/2019 | 6/10/2019 12:44:50 PM | A | CANC |
|
|
Phone #: ###-#### Inspection requested via web by Michael Jerome
|