Inspections for the day of: Monday, June 11, 2001.
Number of inspections: 22
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorSteven Webb
Title 
Phone #794-9491
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD01-00666 BLD-Aging Inspection6/11/20016/11/20016/11/2001 12:00:00 AM PASS
wip 6/11/2001 7:51:00 AM
BLD01-00227 BLD-Aging Inspection6/11/20016/11/20016/11/2001 12:00:00 AM PASS
wip 6/11/2001 7:53:21 AM
BLD01-00091 BLD-Aging Inspection6/11/20016/11/20016/11/2001 12:00:00 AM PASS
wip 6/11/2001 7:51:40 AM
BLD01-00067 BLD-Aging Inspection6/11/20016/11/20016/11/2001 12:00:00 AM PASS
wip 6/11/2001 7:52:24 AM
BLD00-03626 BLD-Aging Inspection6/11/20016/11/20016/11/2001 12:00:00 AM PASS
wip 6/11/2001 7:50:10 AM
BLD01-01133 BLD-Footing6/11/20016/11/20016/11/2001 12:00:00 AMANR
###-####
BLD01-01055 BLD-Framing/Rough-in6/8/20016/11/20016/11/2001 12:00:00 AMAPASS
###-####
BLD01-01137 BLD-Wall cover6/8/20016/11/20016/11/2001 12:00:00 AMAPASS
Scheduled by a contractor via Hello! on 06/08/2001 at 13:46:05. Contact: . Ok to side 6/11/2001 9:17:24 AM
BLD01-00444 BLD-Final6/8/20016/11/20016/11/2001 12:00:00 AMAPASS
Scheduled by a contractor via Hello! on 06/08/2001 at 15:31:00. Contact: ###-####. 6/11/2001 8:30:08 AM C. of C. #21431 issued 6/11/2001 8:32:14 AM
BLD01-00219 BLD-Final6/8/20016/11/20016/11/2001 12:00:00 AMAPASS
Scheduled by a contractor via Hello! on 06/08/2001 at 17:00:54. Contact: ###-####. C. of C. #21432 issued. 6/11/2001 8:39:54 AM
BLD01-01295 BLD-Foundation6/8/20016/11/20016/11/2001 12:00:00 AMAPASS
Scheduled by a contractor via Hello! on 06/08/2001 at 17:30:57. Contact: ###-####.
BLD01-00126 BLD-Final6/10/20016/11/20016/11/2001 12:00:00 AMAFAIL
Scheduled by a contractor via Hello! on 06/10/2001 at 21:38:15. Contact: ###-####. C/N issued-smoke seal needed on fire door. 6/11/2001 10:21:31 AM
BLD01-01410 BLD-Footing6/8/20016/11/20016/11/2001 12:00:00 AMAPART
ft insp smith--- ###-#### wip 6/11/2001 8:11:53 AM
BLD01-01410 BLD-Foundation6/8/20016/11/20016/11/2001 12:00:00 AMPPART
smith-- ###-#### or cell- ###-####---found wall wip 6/11/2001 2:52:55 PM
BLD01-00528 BLD-Final6/8/20016/11/20016/11/2001 12:00:00 AMPFAIL
Scheduled by a contractor via Hello! on 06/08/2001 at 11:46:31. Contact: ###-####.Need electrical final. 6/11/2001 12:54:53 PM
BLD01-00815 BLD-Energy code compliance6/8/20016/11/20016/11/2001 12:00:00 AMPFAIL
Nick ###-#### additional hangers needed nailed and completion of insulation. 6/11/2001 2:26:38 PM
BLD01-00997 BLD-Framing/Rough-in6/8/20016/11/20016/11/2001 12:00:00 AMPPASS
Scheduled by a contractor via Hello! on 06/08/2001 at 14:44:46. Contact: ###-####. ok to cover/SHEAR 6/11/2001 2:47:21 PM
BLD01-00572 BLD-Framing/Rough-in6/8/20016/11/20016/11/2001 12:00:00 AMPPASS
shear nail - jan ###-####
BLD01-00992 BLD-Framing/Rough-in6/11/20016/11/20016/11/2001 12:00:00 AMPFAIL
Scheduled by a contractor via Hello! on 06/11/2001 at 09:35:24. Contact: ###-####. C/N issued 6/11/2001 3:29:15 PM
BLD01-01359 BLD-Footing6/11/20016/11/20016/11/2001 12:00:00 AMPPART
dane ###-#### wip 6/11/2001 1:24:53 PM
BLD01-00791 BLD-Framing/Rough-in6/11/20016/11/20016/11/2001 12:00:00 AMPPASS
Scheduled by Inspector: 420 On 6/11/2001 12:57:22 PM Ok to insulate. 6/11/2001 1:32:49 PM
BLD00-03221 BLD-Foundation6/11/20016/11/20016/11/2001 12:00:00 AMPNR
matt- cell ###-#### found