Inspections for the day of: Friday, June 11, 2010.
Number of inspections: 10
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR06-00331 INSP-Conference6/3/20106/11/20106/15/2010 2:49:32 PMADONE
I left a message on Dons voice mail requesting job status. A follow up inspection has been scheduled.
FIR05-00109 FIR-Aging Inspection6/11/20106/11/20106/15/2010 2:47:55 PM NR
I spoke to Mike with Action Couriers about getting this inspection completed. He wanted to know if Northwest Security could complete this permit instead of ADT. I let him know that a separate permit would be required if another company completed the work. He was going to follow up with ADT. A follow up conference has been set up.
FIR10-00211 INSP-Final Inspection6/11/20106/11/20106/11/2010 3:16:20 PMPPASS
Permit finaled
FIR10-00147 INSP-Sprinkler Rough-in6/11/20106/11/20106/11/2010 2:55:22 PMPPASS
The sprinkler piping is ok to cover.
BLD09-00323 FIRE-Final Inspection6/10/20106/11/20106/11/2010 2:10:16 PMAPART
A temporary occupancy was given with marks and scotts permission until the knox key box thay is on order is received and installed.
BLD10-01104 FIRE-Final Inspection6/11/20106/11/20106/11/2010 11:23:08 AMAFAIL
Provide verification that the existing fire sprinkler system is current with its annual inspection and provide annual inspection for the existing fire extinguisher.
BLD10-01204 FIRE-Final Inspection6/10/20106/11/20106/11/2010 10:47:52 AMAPASS
life safety passed
FIR10-00263 INSP-Final Inspection6/11/20106/11/20106/11/2010 10:33:03 AMPPASS
Permit finaled
BLD09-00945 FIRE-Final Inspection6/10/20106/11/20106/11/2010 9:13:48 AMAPART
Phase 10 life safety passed.
FIR09-00611 INSP-Sprinkler Rough-in6/11/20106/11/20106/11/2010 9:13:10 AMPPASS
Phase 10 sprinkler piping is complete.