Inspections for the day of: Tuesday, June 11, 2013.
Number of inspections: 5
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD13-01052 FIRE-Conference6/11/20136/11/20136/11/2013 3:35:05 PMPDONE
Brad and I did a walk through of Phase 2A of the ED Expansion. I deferred him to the fire dept to approve a revised exiting plan if it deviates from the previously approved plan.
BLD12-03157 FIRE-Final Inspection6/11/20136/11/20136/11/2013 3:22:36 PMPPASS
life safety passed
BLD11-00519 FIRE-Final Inspection6/10/20136/11/20136/11/2013 3:20:28 PMAFAIL
Todays inspection was a cover for the underground supply line. Everything can be covered except for the locations of the thrust blocks which are not complete. Treasure valley fire is supervising the underground installation.
FIR13-00168 INSP-Final Inspection6/10/20136/11/20136/11/2013 10:16:22 AMAPASS
Permit finaled
FIR13-00184 INSP-Sprinkler Rough-in6/10/20136/11/20136/11/2013 12:00:00 AMACANC
troy or joe @ ###-#### Phone #: ###-####