Inspections for the day of: Thursday, June 11, 2015.
Number of inspections: 8
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorThomas Walsh
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD13-03389 FIRE-Final Inspection6/11/20156/11/20156/11/2015 2:43:26 PMPPASS
Need to confirm FS UG supply hydrotest and flush has been witnessed by this office prior to finaling grading permit.
FIR14-00191 INSP-Final Inspection6/11/20156/11/20156/11/2015 2:39:49 PMPPEND
Inspection request to final FS U/G installation, although the hydrotest and flushing could not be confirmed by reviewing completed inspections recorded in permit activities file. I called Forest to confirm that these inspections were witnessed by him, which is contended by the fire sprinkler contractor. Will advise the contractor and GC accordingly.
FIR13-00167 INSP-Sprinkler Rough-in6/11/20156/11/20156/11/2015 2:17:26 PMPNR
Concrete thrust blocks not installed yet - will reschedule inspection, and probably hydrotest for tomorrow.
FIR14-00681 INSP-Final Inspection6/10/20156/11/20156/11/2015 1:40:20 PMAPART
Final inspection of Bldg D, includinfg commons area. Need to remove protective cap on A/S in main lobby (2nd floor). Will sign off when this is completed.
FIR14-00344 INSP-Final Inspection6/10/20156/11/20156/11/2015 1:34:19 PMAPART
Final inspection of Bldg. D and commons area. Lobby sprinkler at 2nd floor level has protective cap still on. Will need to get a lift to access. Will reschedule final signoff, otherwise rest of system inspected OK
FIR14-00362 INSP-Final Inspection6/10/20156/11/20156/11/2015 1:29:21 PMAPART
Final inspection of U/G parking garage wet system.
NOTE: Fire caulking needed at stair # 3 pipe penetration. Also need to inspect fire pump room, as this room is under this permit.
FIR14-00815 INSP-Sprinkler Rough-in6/10/20156/11/20156/11/2015 9:45:51 AMAPART
Rough to cover inspection for 2nd floor corridor for section 1 - OK to Cover.
Also coverage for rotunda and skylight in clubhouse.
NOTE: Need HT head for top of skylight.
FIR13-00725 INSP-Sprinkler Rough-in/Hydro6/11/20156/11/20156/11/2015 8:52:06 AMPPASS
Hydrotest of wet pipe system protecting Makers Room at the top level of the parking garage - 200 psi @ 2 hours - PASSED