FIR15-00322
| INSP-Supply line flush | 6/10/2015 | 6/11/2015 | 6/11/2015 3:02:17 PM | P | FAIL |
|
|
Service not turned on to the building
|
FIR15-00360
| INSP-Supply line flush | 6/10/2015 | 6/11/2015 | 6/11/2015 3:01:38 PM | P | FAIL |
|
|
Service not turned on to the building
|
FIR15-00320
| INSP-Sprinkler Rough-in | 6/10/2015 | 6/11/2015 | 6/11/2015 3:00:42 PM | P | PASS |
|
|
Overhead sprinkler piping/tenting approved for cover
|
FIR15-00359
| INSP-Sprinkler Rough-in/Hydro | 6/10/2015 | 6/11/2015 | 6/11/2015 2:58:08 PM | P | FAIL |
|
|
Service not turned on to the building
|
FIR14-00801
| INSP-Final Inspection | 6/11/2015 | 6/11/2015 | 6/11/2015 2:10:39 PM | P | FAIL |
|
|
This is not a final inspection, this was an underground cover inspection (Pot Marked Inspection for proper cover depth) and an underground flush. Pipe is at an approved depth and supply line is flushed/complete
|
BLD15-01764
| FIRE-Final Inspection | 6/11/2015 | 6/11/2015 | 6/11/2015 1:18:25 PM | P | FAIL |
|
|
Need to have fire extinguisher mounted in common area of travel, dead bolt on rear door needs to be removed and single action lockable hardware installed.
|
FIR15-00112
| INSP-Sprinkler Rough-in | 6/11/2015 | 6/11/2015 | 6/11/2015 11:01:59 AM | P | PASS |
|
|
Noted areas approved (Basement Level) for cover in red on the onsite city approved drawings.
|
FIR14-00801
| INSP-Conference | 6/10/2015 | 6/11/2015 | 6/11/2015 10:05:57 AM | A | DONE |
|
|
Verfied with on site contact, "pot marks" are being provided to verify underground piping cover.
|
FIR15-00003
| INSP-Final Inspection | 6/11/2015 | 6/11/2015 | 6/11/2015 12:00:00 AM | P | DONE |
|
|
as per Jim Page ok to final
|