FIR12-00251
| INSP-Final Inspection | 6/11/2012 | 6/12/2012 | 6/13/2012 5:19:00 PM | A | PASS |
|
|
Rough-in and final inspections both passed.
|
FIR12-00189
| INSP-Sprinkler Rough-in/Hydro | 6/11/2012 | 6/12/2012 | 6/12/2012 4:11:54 PM | P | NR |
|
|
Hydrostatic test rescheduled per contractor request.
|
FIR12-00019
| FIR-Aging Inspection | 6/12/2012 | 6/12/2012 | 6/12/2012 4:10:23 PM | | PEND |
|
|
|
FIR12-00017
| FIR-Aging Inspection | 6/12/2012 | 6/12/2012 | 6/12/2012 4:09:23 PM | | PEND |
|
|
Construction underway. Need inspection request for work completed to date when ready.
|
BLD12-01320
| FIRE-Conference | 6/12/2012 | 6/12/2012 | 6/12/2012 4:04:10 PM | P | NR |
|
|
On site conference with the property owner regarding min. requirements for occupancy approvals including signage and hardware at the main entry/exit and fire extinguisher guidelines.
|
FIR11-00651
| INSP-Sprinkler Rough-in | 6/12/2012 | 6/12/2012 | 6/12/2012 3:59:37 PM | P | PART |
|
|
Overhead rough-in and cover inspection for the CPVC wet system piping and drop sprinklers passed. Grid ceiling cover approved.
|
BLD12-00928
| FIRE-Final Inspection | 6/12/2012 | 6/12/2012 | 6/12/2012 3:55:51 PM | P | PASS |
|
|
Fire life safety finaled.
|
FIR12-00186
| INSP-Sprinkler Rough-in | 6/12/2012 | 6/12/2012 | 6/12/2012 3:54:57 PM | A | PART |
|
|
Added coverage at the mens restroom okayed.
|
BLD12-01388
| FIRE-Final Inspection | 6/12/2012 | 6/12/2012 | 6/12/2012 3:53:17 PM | A | PART |
|
|
Discussion with tenant rep. regarding items remaining for final and project occupancy schedule.
|
FIR12-00253
| INSP-Final Inspection | 6/12/2012 | 6/12/2012 | 6/12/2012 3:51:34 PM | A | PART |
|
|
Fire sprinkler modifications in the "Andy's supply" tenant area only approved for final.
|