FIR13-00116
| INSP-Sprinkler Rough-in/Hydro | 6/12/2013 | 6/12/2013 | 6/12/2013 4:57:11 PM | P | PART |
|
|
UG fire supply line hydrostatic test completed satisfactory.
|
BLD13-01454
| FIRE-Final Inspection | 6/12/2013 | 6/12/2013 | 6/12/2013 4:55:59 PM | P | NR |
|
|
|
BLD13-01203
| FIRE-Sprinkler Rough-in | 6/12/2013 | 6/12/2013 | 6/12/2013 4:55:30 PM | A | PART |
|
|
Fire sprinkler mods okay to cover at the drop ceilings 4th floor.
|
BLD13-01113
| FIRE-Conference | 6/12/2013 | 6/12/2013 | 6/12/2013 4:53:24 PM | A | DONE |
|
|
Regarding hood suppression work and fire life safety inspection items.
|
BLD13-00464
| FIRE-Final Inspection | 6/11/2013 | 6/12/2013 | 6/12/2013 4:50:45 PM | A | PASS |
|
|
Remainder of work completed. Fire life safety inspection passed.
|