Inspections for the day of: Thursday, June 12, 2014.
Number of inspections: 13
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorJim Johnson
TitlePLM-INSPECTOR
Phone #794-9476
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
PLM14-00357 Final6/12/20146/12/20146/12/2014 4:18:20 PMPPART
Phone #: ###-#### >> Inspection requested via web by Brian Johansen
PLM14-01631 Plumbing Rough-in6/11/20146/12/20146/12/2014 2:53:30 PMPFAIL
JOB # 17474. Phone #: ###-#### >> Inspection requested via web by Ann Marie Reyes test failed on D W V on the north side of building need to retest contractor to recall when ready correction notice on site in mechanical room by double check valve NOTE- water system test ok and D W V on south side of building test ok
PLM14-01467 Plumbing Rough-in6/11/20146/12/20146/12/2014 2:36:09 PMAPART
JOB CONTACT - CHRIS ###-#### Phone #: ###-#### >> Inspection requested via web by BECCA DUMMER in wall rough-in for d w v and over head vents test ok
PLM13-02942 Final6/11/20146/12/20146/12/2014 1:09:50 PMPFAIL
Phone #: ###-#### >> Inspection requested via web by James Staley need to have co2 alarm,s installed for final called contractor contractor to recall when ready
PLM14-01625 Water and/or Sewer6/11/20146/12/20146/12/2014 12:04:34 PMAPASS
PLM14-01625 DOC - Permit Finaled6/12/20146/12/20146/12/2014 12:02:23 PMAPASS
PLM14-01608 Water Heater Final6/11/20146/12/20146/12/2014 10:49:32 AMAPASS
This is a vacant home. Please contact Daniel and he will give you the lockbox code to enter. Any questions please contact him. Thank you. Phone #: ###-#### >> Inspection requested via web by Ben Davis
PLM14-01623 Water Heater Final6/11/20146/12/20146/12/2014 10:32:19 AMAPASS
Juanita ###-#### or ###-#### Phone #: ###-#### >> Inspection requested via web by curtis rowe
PLM14-01568 Groundwork6/11/20146/12/20146/12/2014 10:24:20 AMAPART
Call me when you are heading out to this job Jim and I will make sure you get in. The groundwork is done as well as the rough-in. Thanks! Phone #: ###-#### >> Inspection requested via web by Troy Woolston groundwork and partical rough-in on back wall test ok ok to cover still need to have wall built and finish rough-in in front of store area contractor to recall for rough-in when ready
PLM14-00763 Plumbing Rough-in6/11/20146/12/20146/12/2014 9:06:04 AMAPASS
>> Inspection requested via web by David Salamon
PLM14-00762 Plumbing Rough-in6/11/20146/12/20146/12/2014 9:05:49 AMAPASS
>> Inspection requested via web by David Salamon
PLM13-02589 Final6/11/20146/12/20146/12/2014 8:35:48 AMAPASS
Phone #: ###-#### >> Inspection requested via web by David Salamon
PLM13-03276 Plumbing Rough-in6/12/20146/12/20146/12/2014 8:19:29 AMACANC
2nd floor Phone #: ###-#### >> Inspection requested via web by j mait downer jr Inspection cancelled from web by: j mait downer jr