PDS Online
Making
Boise
the most livable city in the country.
Home
Permits
Search by Permit Number
How to search by permit number
Search by Address
Search by Customer Number
Search by Current Planning Number
Search in Project by Permit Number
Search by Project Name
Inspections
Search by Permit Number
Search by Request Date
Search by Company Name
Fees
Impact Fees Estimate Calculator
Other Searches
Search for Licensed Contractors
Search Parcel by Address
Search Historical Surveys
Reports
Daily Reports
Weekly Reports
Monthly Reports
Home
/
Inspections
/
Inspector Activity
Inspections for the day of:
Monday, June 12, 2017
.
Number of inspections:
13
Percentage of inspections complete:
100 %
Percentage of inspections not complete:
0 %
Contact Information
Inspector
Andy J. Long
Title
EROSION INSPECTOR
Phone #
794-8996
Permit Number
Description
Received
Requested
Completed
AM/PM
Disposition
ESC17-00636
Site Preparation
6/12/2017
6/12/2017
6/13/2017 8:16:58 AM
P
PASS
Mark Phone #: ###-####
Subdivision BMPs installed. Approved for construction.
ESC17-00571
General Inspection
6/8/2017
6/12/2017
6/13/2017 7:55:38 AM
A
PART
Excavator placed backfill around perimeter of site where there is no sediment protection. Needs to be cleaned of sidewalk by end of week.
Permit sign is posted, sediment protection in receiving inlet. Inspection conducted 6/12 AM, follow up scheduled for 6/16
ESC16-00115
Aging Inspection
6/12/2017
6/12/2017
6/13/2017 7:53:01 AM
CANC
ESC16-00691
Aging Inspection
6/12/2017
6/12/2017
6/13/2017 7:52:53 AM
CANC
ESC15-00955
General Inspection
6/12/2017
6/12/2017
6/13/2017 7:52:44 AM
CANC
ESC16-01088
General Inspection
6/12/2017
6/12/2017
6/12/2017 11:13:33 AM
A
PASS
WIP on preparing parking lot for paving. No significant trackout, stormwater retained onsite. Approved.
ESC16-00305
Aging Inspection
6/12/2017
6/12/2017
6/12/2017 11:07:09 AM
CANC
ESC16-00961
Site Final
6/12/2017
6/12/2017
6/12/2017 10:50:47 AM
A
NR
Need to remove DI bags west of home on Ardyce. Home is complete and stabilized, no other corrections.
Notified CBH RPs
ESC16-01461
Site Final
6/12/2017
6/12/2017
6/12/2017 10:39:51 AM
P
PASS
Home complete and landscaped. Street and gutter has been swept BLD still open. Temporary sediment protection on Ardyce and Coolwater may remain for the adjacent SFHs now in progress by CBH. No ESC corrections required.
ESC16-00722
Site Final
6/12/2017
6/12/2017
6/12/2017 10:23:27 AM
A
NR
Construction activities near complete. Temp. occupancy granted. Need to complete stablization & landscaping, sweep up and clean loose dirt and construction materials in parking lot. Need to remove DI bag in onsite drainage and also
Written correction requested posted.
ESC16-00722
General Inspection
6/12/2017
6/12/2017
6/12/2017 10:13:49 AM
A
CANC
ESC17-00572
Site Preparation
6/7/2017
6/12/2017
6/12/2017 10:07:20 AM
A
PASS
9:00 AM Jake Miller ###-####
ESC plan and SWPPP onsite. RP and excavation crew attended pre-construction site meeting. Permit sign posted. Silt fence properly installed along the downslope north construction limit. Will be hauling off dirt, will install angular rock construction entrance to replace existing small rock tracking pad. MS4 sediment protection installed on Executive. Notified crew of concrete washout, fugitive dust, and trash containment requirements.
Approved for constructon.
ESC15-01532
General Inspection
6/12/2017
6/12/2017
6/12/2017 8:28:33 AM
PEND
temp BMP removal/cleanup to be completed when high river levels recede.