FIR11-00650
| FIR-Aging Inspection | 6/13/2012 | 6/13/2012 | 6/20/2012 3:45:41 PM | | NR |
|
|
work is in progress
|
FIR12-00078
| INSP-Final Inspection | 6/7/2012 | 6/13/2012 | 6/14/2012 2:48:26 PM | P | CANC |
|
|
Steve Phone #: ###-####
|
FIR12-00116
| INSP-Sprinkler Rough-in | 6/12/2012 | 6/13/2012 | 6/13/2012 3:53:52 PM | P | PASS |
|
|
Overhead hydro tests on the dry and wet systems passed. Still need 24 hour air test on the dry. Rough-in for the sprinkler piping in the data room passed and the piping can be covered. The wet system piping rough-in passeed. Plan review needs to be contacted about modified hydraulic calculations due to the additional 2" elbows that have been added between the remote area and the supply.
|
FIR12-00082
| INSP-Final Inspection | 6/7/2012 | 6/13/2012 | 6/13/2012 3:45:58 PM | P | PASS |
|
|
Permit finaled
|
BLD12-01157
| FIRE-Final Inspection | 6/12/2012 | 6/13/2012 | 6/13/2012 2:44:28 PM | A | PART |
|
|
A TCO for 30 days under the condition that only the kitchen area may be occupied until the final CO has been issued was given with scott and romeo's permission until the occupant load is reduced and the fire sprinkler coverage is modified. Per Jeff with treasure valley fire protection drawings should be in to plan review by today or tomorrow.
|
FIR12-00085
| INSP-Final Inspection | 6/7/2012 | 6/13/2012 | 6/13/2012 2:37:54 PM | P | PASS |
|
|
Permit finaled
|
BLD11-01267
| FIRE-Final Inspection | 6/13/2012 | 6/13/2012 | 6/13/2012 2:02:50 PM | P | FAIL |
|
|
Todays inspection was for area "A" and "B", first and second floors. Many emergency lights are not functioning or have not been installed. Several exit signs are not working. Fire extinguisher placement appears ok. Fire hydrant barrel orientation has been modified as requested. Per the revised building and fire review notes and verified by phone conversation with scott arellano the Area of Refuge communication system is not required but since a system has been installed it must function. Per scott the system does not need to call out but must atleast contact a central location. Currently the head end equipment is located at the fire alarm system remote annunciator in the main lobby. Scott was ok with this location.
|
BLD11-02789
| FIRE-Conference | 6/8/2012 | 6/13/2012 | 6/13/2012 1:52:25 PM | A | DONE |
|
|
I went over life safety requirements with Bill. Found two exit signs with no battery backup.Need address numbers and fire extinguishers.
|
FIR12-00063
| INSP-Final Inspection | 6/7/2012 | 6/13/2012 | 6/13/2012 1:50:44 PM | P | PASS |
|
|
Permit finaled
|
FIR11-00662
| INSP-Alarm Testing | 6/12/2012 | 6/13/2012 | 6/13/2012 10:31:49 AM | A | DONE |
|
|
Todays inspection included reverification of the fire smoke damper activation and the west side elevator recall. Also incuded were EOL voltage verification for areas "A" and "B", first and second floor audio/visuals. To finish these this area I need the horns in rooms 215 and 220 repaired and test the separate notification circuits at the first and second floor fire wall in area "B".
|
FIR12-00161
| INSP-Final Inspection | 6/12/2012 | 6/13/2012 | 6/13/2012 10:28:17 AM | A | PART |
|
|
Fire sprinkler work is complete for the first and second floors of areas "A " and "B".
|
BLD12-00002
| FIRE-Final Inspection | 6/12/2012 | 6/13/2012 | 6/13/2012 10:26:37 AM | A | PASS |
|
|
No parking signs installed via ACHD. Life safety passed
|
BLD11-02685
| FIRE-Final Inspection | 6/12/2012 | 6/13/2012 | 6/13/2012 10:25:59 AM | A | PASS |
|
|
No fire life safety sign off required for this permit.
|
BLD12-00187
| FIRE-Final Inspection | 6/13/2012 | 6/13/2012 | 6/13/2012 7:50:18 AM | P | PASS |
|
|
Life safety passed
|
FIR12-00277
| INSP-Final Inspection | 6/11/2012 | 6/13/2012 | 6/13/2012 7:48:00 AM | A | PASS |
|
|
Permit finaled. Request at 7am//Steve Phone #: ###-####
|