FIR12-00252
| INSP-Alarm Testing | 6/12/2013 | 6/13/2013 | 6/17/2013 8:02:08 AM | P | FAIL |
|
|
New notification appliances need to meet location guidelines per NFPA 72. Type and cd settings need to match approved plan. DSC permit must be finaled prior.
|
FIR13-00116
| INSP-Sprinkler Rough-in | 6/12/2013 | 6/13/2013 | 6/17/2013 7:57:09 AM | P | PART |
|
|
Overhead rough-in at the west and east side restrooms, RR vestibules, and patio areas are approved for cover as marked and dated on stamped plan set.
|
FIR13-00243
| INSP-Sprinkler Rough-in | 6/13/2013 | 6/13/2013 | 6/17/2013 7:51:58 AM | P | PART |
|
|
Overhead rough-in inspection completed- field modifications to be reflected on as-builts. Cover approval pending verification of insulation for cold cavity protection.
|
BLD13-01382
| FIRE-Final Inspection | 6/12/2013 | 6/13/2013 | 6/14/2013 6:40:04 AM | A | PASS |
|
|
Fire life safety inspection passed - manual thumbturns at the main entry/exit to be removed prior to structural final as agreed.
|
BLD13-01472
| FIRE-Final Inspection | 6/12/2013 | 6/13/2013 | 6/13/2013 11:25:14 AM | A | PASS |
|
|
Life safety inspection passed provided commercial grade single function hardware is provided at the new door per plan red-line annotations. Also need to post "door to remain.." signage at the main entry/exit door. Items to be finished prior to structural final as discussed.
|