Inspections for the day of: Tuesday, June 14, 2005.
Number of inspections: 7
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorForrest France
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR05-00331 INSP-Sprinkler Rough-in/Hydro6/14/20056/14/20056/14/2005 3:57:36 PMPPASS
Fire sprinkler passed inspection.
FIR05-00155 INSP-Sprinkler Rough-in6/14/20056/14/20056/14/2005 3:33:01 PMPFAIL
Pendent heads in kitchen at range hood need to be proper temp. rating, need dry SW at closet 163 as shown on plans, attatch retaining straps in rooms 123 and 127, head in hall 108 is overspaced, provide aux. drain at trapped 4" main in sanctuary, upright head in mezz. SE corner is overspaced, hangers overspaced on last pcs. in multi-purpose room, FDC must meet requirements of note #25 on plan review.
BLD05-00669 FIRE-Final Inspection6/13/20056/14/20056/14/2005 3:25:37 PMPFAIL
Provide building address, provide fire ext. with current tag mounted in basement, install 2nd piece canopies on SW heads. Contractor seeks TO for basement area.
MIS05-00086 FIR-Final6/13/20056/14/20056/14/2005 10:19:50 AMAFAIL
Repair two emergency lights at exit signs in corridor and south main exit, post correct occupant load.
BLD04-02348 FIRE-Conference6/13/20056/14/20056/14/2005 9:18:12 AMADONE
Confrence to discuss fire water supply vault installation under excavation and grading permit.
BLD04-01632 FIRE-Supply Line Cover6/14/20056/14/20056/14/2005 12:00:00 AMAPART
Underground fire supply vaults are allowed to be installed under this excavation and grading permit per Sam Rogers. Vaults match submitted plans of type and installation method, OK to cover.
MIS05-00086 FIR-Final6/14/20056/14/20056/14/2005 12:00:00 AMAPASS
Fire life safety finaled.