FIR07-00500
| INSP-Final Inspection | 6/14/2007 | 6/14/2007 | 6/14/2007 6:41:17 PM | P | PASS |
|
|
Permit finaled
|
FIR06-00664
| INSP-Sprinkler Rough-in/Hydro | 6/14/2007 | 6/14/2007 | 6/14/2007 3:45:53 PM | P | PASS |
|
|
All above ground hydro tests passed except for the second floor and the fdc. The roof manifold was also flowed. The fire truck put out a max of 161psi which gave us 29 psi at the roof and 904gpm at the outlet. 141psi at the truck gave 100psi at the roof.
|
FIR06-00178
| INSP-Final Inspection | 6/12/2007 | 6/14/2007 | 6/14/2007 11:31:31 AM | A | FAIL |
|
|
there were no city review notes or approved data sheets. See the city approved plans for locations where a/v's need to be added in exam rooms and candellas changed to what is marked on the approved plans.. Also it appears that all of the new duct smoke detectors are improperly placed and the incorrect sample tubes utilized. A manometer test will be required. Only one detector was tested and that was just to make sure the detector shut the unit down imediately. The supervision of the NAC panels by the facp has been tested ok. All of the existing device locations are too low to meet code compliance which Bob was going to verify could remain. One existing device has not been changed out to a new device and is marked on the plans.
|
FIR07-00215
| FIR-Aging Inspection | 6/14/2007 | 6/14/2007 | 6/14/2007 10:16:50 AM | | PASS |
|
|
permit finaled
|