FIR11-00194
| INSP-Sprinkler Rough-in | 6/14/2011 | 6/14/2011 | 6/14/2011 3:55:06 PM | P | PART |
|
|
Okay to cover fire sprinkler system modifications at the manager, office and reception rooms. See dated and clouded areas on plans.
|
BLD11-00894
| FIRE-Conference | 6/13/2011 | 6/14/2011 | 6/14/2011 3:39:04 PM | P | DONE |
|
|
On site meeting with contractor regarding fire life safety issues, review notes, red-line annotations, project related fire sprinkler permit work, existing fire alarm system, fire extinguisher locations, exit signage/EM lighting, accessibility upgrades.
|
FIR11-00153
| INSP-Conference | 6/14/2011 | 6/14/2011 | 6/14/2011 3:35:26 PM | P | DONE |
|
|
Regarding after hours inspection schedule.
|
FIR08-00239
| INSP-Sprinkler Rough-in | 6/13/2011 | 6/14/2011 | 6/14/2011 3:34:33 PM | A | PART |
|
|
Inspection for cover at 3rd floor building #3 tenant units only okayed with exceptions in unit 304 as marked on plan set. Also inspected coverage/ non-combustible finishes at 1st thru 4th floor concealed spaces behind and above fireplace enclosures. Note, some locations are sprinklered and others are sheetrocked to meet allowable exceptions per NFPA 13. Also noted 1st floor blind space room adjacent the the electrical room building #2 SW corner to be sprinklered.
|
FIR11-00141
| INSP-Final Inspection | 6/10/2011 | 6/14/2011 | 6/13/2011 12:00:00 AM | A | CANC |
|
|
JOSH Phone #: ###-#### //cancelled per Josh w/Fire Sentry Sys. 6/13/11
|