BLD12-00746
| FIRE-Final Inspection | 6/14/2012 | 6/14/2012 | 6/14/2012 4:23:54 PM | A | NR |
|
|
|
FIR11-00651
| INSP-Sprinkler Rough-in/Hydro | 6/14/2012 | 6/14/2012 | 6/14/2012 4:22:45 PM | P | PART |
|
|
Wet system passed hydrostatic test.
|
FIR12-00066
| INSP-Alarm Testing | 6/14/2012 | 6/14/2012 | 6/14/2012 3:45:59 PM | P | PEND |
|
|
Final scheduled 6/15 AM.
|
FIR12-00296
| INSP-Final Inspection | 6/14/2012 | 6/14/2012 | 6/14/2012 3:44:26 PM | P | PASS |
|
|
Scope of demo permit work completed satisfactory. Final status approved.
|
FIR11-00587
| INSP-Sprinkler Rough-in | 6/14/2012 | 6/14/2012 | 6/14/2012 3:41:22 PM | P | PART |
|
|
Four new heads and related branchline piping at the new MRI room fed from the preaction system (project phase 3) are okay for cover.
|
BLD11-01743
| FIRE-Sprinkler Rough-in | 6/14/2012 | 6/14/2012 | 6/14/2012 3:39:20 PM | P | PART |
|
|
Overhead fire sprinkler work at the grid ceilings approved for cover.
|
FIR12-00154
| INSP-Conference | 6/14/2012 | 6/14/2012 | 6/14/2012 3:37:08 PM | A | DONE |
|
|
Regarding project inspection schedule.
|
BLD12-00581
| FIRE-Final Inspection | 6/14/2012 | 6/14/2012 | 6/14/2012 3:36:03 PM | A | NH |
|
|
|
BLD12-01090
| FIRE-Final Inspection | 6/13/2012 | 6/14/2012 | 6/14/2012 3:35:24 PM | A | PASS |
|
|
Life safety inspection passed. Scope of permit work completed.
|