Inspections for the day of: Monday, June 15, 2009.
Number of inspections: 7
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorClint A Smith
TitleEROSION CONTROL INSPECTOR
Phone #794-8996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC07-00070 General Inspection6/15/20096/15/20096/15/2009 4:42:03 PMPPASS
Site looks good. Stabilization of the hillside is coming along good. Vegitation is becoming established where hydro seed was applied. After the rain event of the past two weeks all has held up well.
ESC07-00986 BMP Violation6/15/20096/15/20096/15/2009 2:09:49 PMPFAIL
Correction Notice:
1. Provide sediment controls along Allumbaugh.
2. Clean up and capture all turbid water at the storm drains along Allumbaugh.
3. Clean up all sediment and debris along Allumbaugh. Failure to comply will result in a Stop Work Order and further enforcement. Will re-inspect on 6/16/09 AM.
ESC09-00006 Site Final4/30/20096/15/20096/15/2009 1:25:34 PMAPASS
ESC08-00539 BMP Violation6/15/20096/15/20096/15/2009 1:24:58 PMPFAIL
Verbal to RP:
Protect all disturbed area with some type ofv sediment bmps along Five Mile Rd.
Protect the storm drain inlets within parking lot and the 1 storm drain at the corner of Five Mile and project area. Will re-inspect on 6/17/09.
ESC08-01043 Site Preparation6/12/20096/15/20096/15/2009 11:49:34 AMAPART
In the process of implimenting the BMP's per there erosion control plan.
ESC09-00286 General Inspection6/15/20096/15/20096/15/2009 11:49:00 AMPPART
Found that n the west end of project that the out fall from the runoff from the foothill subdivision was discharging turbid run off into the penn canal. Nothing was generated from any construction activies. Also the consultant and i observed a storm drain inlet on Barber rd needed to be protected. No major issues with any of the construction activies.
ESC07-01595 Site Final6/9/20096/15/20096/11/2009 11:27:15 AMAPASS