FIR11-00270
| INSP-Conference | 6/15/2011 | 6/15/2011 | 6/15/2011 4:38:45 PM | P | DONE |
|
|
Conversation with contractor regarding sprinkler monitoring requirements and site inspection schedule.
|
BLD11-00323
| FIRE-Sprinkler Rough-in | 6/15/2011 | 6/15/2011 | 6/15/2011 4:36:55 PM | P | PART |
|
|
Okay to cover fire sprinkler work at three rooms as marked on plans including the office, reception and managers rooms.
|
BLD11-00715
| FIRE-Final Inspection | 6/15/2011 | 6/15/2011 | 6/15/2011 4:34:14 PM | P | PASS |
|
|
Fire life safety final passed. Existing rated corridor to be maintained or provide QR type sprinklers throughout the floor level per IBC 2009.
|
FIR11-00188
| INSP-Conference | 6/15/2011 | 6/15/2011 | 6/15/2011 4:30:09 PM | P | DONE |
|
|
|
FIR10-00473
| INSP-Final Inspection | 6/15/2011 | 6/15/2011 | 6/15/2011 4:27:19 PM | P | PART |
|
|
Final pending overhead permit work.
|
FIR11-00153
| INSP-Alarm Testing | 6/15/2011 | 6/15/2011 | 6/15/2011 4:24:26 PM | A | PART |
|
|
Functional test scheduled 6/16
|
FIR08-00239
| INSP-Sprinkler Rough-in | 6/15/2011 | 6/15/2011 | 6/15/2011 4:21:41 PM | A | PART |
|
|
|