BLD12-01251
| FIRE-Final Inspection | 6/14/2012 | 6/15/2012 | 6/15/2012 11:09:11 AM | A | PASS |
|
|
Life safety passed
|
BLD11-01268
| FIRE-Conference | 6/14/2012 | 6/15/2012 | 6/15/2012 10:40:37 AM | A | DONE |
|
|
The additional emergency lighting in the second floor common rooms and the first floor movie room is not going to be required per Dan Stuart in plan review.
|
BLD12-00136
| FIRE-Final Inspection | 6/14/2012 | 6/15/2012 | 6/15/2012 9:15:17 AM | A | PASS |
|
|
Fire life safety passed
|
BLD12-00617
| FIRE-Final Inspection | 6/15/2012 | 6/15/2012 | 6/15/2012 8:58:29 AM | P | PASS |
|
|
Life safety passed
|
BLD11-03012
| FIRE-Final Inspection | 6/14/2012 | 6/15/2012 | 6/15/2012 8:48:53 AM | A | PART |
|
|
The life safety is passed for the mezzanine, first and second floors. Per Jennifer a temporary occupancy is ok without the alarm being installed since the fire alarm system is voluntary and not required.
|
BLD11-02789
| FIRE-Final Inspection | 6/13/2012 | 6/15/2012 | 6/15/2012 8:39:33 AM | A | PASS |
|
|
Life safety passed
|
FIR12-00204
| INSP-Final Inspection | 6/13/2012 | 6/15/2012 | 6/15/2012 8:35:52 AM | A | PASS |
|
|
Permit finaled. Suppression system functioned correctly.
|