FIR15-00236
| INSP-Sprinkler Rough-in | 6/15/2015 | 6/15/2015 | 6/16/2015 9:36:07 AM | P | PASS |
|
|
Overhead 24 hour Air Test passed/complete on the dry system covering the south loading dock.
|
FIR15-00320
| INSP-Sprinkler Rough-in/Hydro | 6/15/2015 | 6/15/2015 | 6/15/2015 3:07:41 PM | P | PASS |
|
|
Hydrostatic test for 1st level, 2nd level and FDC passed/complete
|
BLD15-01170
| FIRE-Final Inspection | 6/15/2015 | 6/15/2015 | 6/15/2015 2:21:38 PM | P | PASS |
|
|
Previously noted items corrected, life fire safety passed/complete
|
FIR15-00322
| INSP-Sprinkler Rough-in | 6/12/2015 | 6/15/2015 | 6/15/2015 2:05:37 PM | P | FAIL |
|
|
Overhead piping not approved for cover, tenting still needs installed, piping not complete for rough to cover inspection.
|
FIR15-00322
| INSP-Supply line flush | 6/12/2015 | 6/15/2015 | 6/15/2015 1:24:58 PM | P | PASS |
|
|
Underground piping flush passed/complete
|
FIR14-00839
| INSP-Sprinkler Rough-in/Hydro | 6/15/2015 | 6/15/2015 | 6/15/2015 12:55:43 PM | P | PASS |
|
|
Hydrostatic test complete on the three wet systems
|
FIR15-00377
| INSP-Final Inspection | 6/15/2015 | 6/15/2015 | 6/15/2015 9:49:27 AM | P | PASS |
|
|
Fire sprinkler scope of work inspection passed/complete
|
FIR15-00417
| INSP-Sprinkler Rough-in | 6/15/2015 | 6/15/2015 | 6/15/2015 9:23:56 AM | P | PASS |
|
|
Fire sprinkler inspection passed/complete
|