Inspections for the day of: Monday, June 15, 2020.
Number of inspections: 3
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR19-00931 INSP-Final Inspection6/14/20206/15/20206/15/2020 3:52:13 PMPPASS
Permit finaled. Phone #: 2088301311 >> Inspection requested via mobile web by Nathan Price
FIR19-00793 INSP-Sprinkler Rough-in6/15/20206/15/20206/15/2020 3:07:56 PMPFAIL
The rough-in for the most part is good. But the 2" main piping is not shown for one feed and installed in the wrong size for the other feed. Plans need to show the heads in the closets on the 4th floor. Need insulation on breeze way piping, Need tenting repaired on the 4th and 3rd floors. It appears the standpipe may be in the wrong location. Need sprinkler coverage in the Roof Access/FACP room. Tanner *screened* Phone #: ###-####
FIR19-00933 INSP-Sprinkler Rough-in/Hydro6/12/20206/15/20206/15/2020 11:07:11 AMAPART
First floor rough in passed. Piping can be covered. The second floor high/lobby and west stairs are not done yet. Hydro on first floor was witnessed with no pressure loss. Second floor hydro have a visible loss on the guage and not all piping is cut in. Phone #: ###-#### Inspection requested via web by Brian Carlisle