Inspections for the day of: Tuesday, June 16, 2020.
Number of inspections: 12
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorJim Page
TitleFIRE INSPECTOR
Phone #208-914-5431
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR20-00335 INSP-Sprinkler Rough-in6/15/20206/16/20206/16/2020 3:44:09 PMPPART
Rough in inspection for overhead fire sprinkler piping is complete, will need verification on R value for foam insulation before cover can be approved.

Phone #: ###-#### Inspection requested via web by Jonathan LaFond
FIR19-00888 INSP-Supply line flush6/16/20206/16/20206/16/2020 2:06:17 PMPCANC
Flush rescheduled for 17JUNE2020 per conversation with SUEZ and point of contact. Could not flush until water sample acceptance for the new water service.

Jeff Chaney is the contact. Thanks so much! Phone #: ###-#### Inspection requested via web by Stan Beus
FIR19-00623 INSP-Sprinkler Rough-in/Hydro6/15/20206/16/20206/16/2020 2:00:24 PMAPART
Hydrostatic test witnessed for dry system and wet system number 2, no pressure loss observed at riser provided gauges. 24 hour air test started for dry stsrtem at 2PM with 45PSI on gauge.

Rick *screened* Phone #: ###-####
BLD20-00301 FIRE-Final Inspection6/15/20206/16/20206/16/2020 10:49:10 AMAPASS
No fire sprinklers, no fire alarms, fire extinguishers are placed with current inspection tags. Final life fire safety inspection for area of work is complete, signature provided on permit sign off card.

Screened-Kent Phone #: ###-####
FIR20-00058 INSP-Final Inspection6/16/20206/16/20206/16/2020 10:28:41 AMPPASS
Final fire alarm inspection for area of work is complete.

This is a final for FIR20-00058 contact Jeff when you are at B17C lobby. Phone #: ###-#### Inspection requested via web by Jeff Roberts
FIR20-00288 INSP-Final Inspection6/15/20206/16/20206/16/2020 9:01:00 AMAPASS
Final fire sprinkler inspection for scope of work is complete.

Contact Steve Johnson (cell ###-####) Phone #: ###-#### Inspection requested via web by Steve Johnson
FIR20-00251 INSP-Sprinkler Rough-in6/15/20206/16/20206/16/2020 9:00:26 AMAPASS
Rough to cover inspection for area of work is complete, approved for cover.

Contact Steve Johnson (cell ###-####) Phone #: ###-#### Inspection requested via web by Steve Johnson
FIR20-00249 INSP-Sprinkler Rough-in6/15/20206/16/20206/16/2020 8:59:37 AMAPASS
Rough to cover inspection for area of work is complete, approved for cover.

Contact Steve Johnson (cell ###-####) Phone #: ###-#### Inspection requested via web by Steve Johnson
FIR20-00250 INSP-Sprinkler Rough-in6/15/20206/16/20206/16/2020 8:58:58 AMAPASS
Rough to cover inspection for area of work is complete, approved for cover.

Contact Steve Johnson (Cell ###-####) Phone #: ###-#### Inspection requested via web by Steve Johnson
FIR20-00253 INSP-Sprinkler Rough-in6/15/20206/16/20206/16/2020 8:57:48 AMAPASS
Rough to cover inspection for area of work is complete, approved for cover.

Contact Steve Johnson (cell ###-####) Phone #: ###-#### Inspection requested via web by Steve Johnson
BLD20-00659 FIRE-Final Inspection6/15/20206/16/20206/16/2020 7:07:21 AMAPASS
Fire sprinkler inspection complete, fire alarm inspection is complete, fire extinguishers are in common areas with current inspection tags. Final life fire safety inspection for area of work is complete, signatures provided on permit sign off card.

Phone #: ###-#### Inspection requested via web by James Hibbard
FIR20-00324 INSP-Final Inspection6/15/20206/16/20206/16/2020 7:05:23 AMAPASS
Final fire alarm inspection for area of work is complete.

Phone #: ###-#### Inspection requested via web by Rick Groom, Coordinated for 7AM with inspector.