Inspections for the day of: Wednesday, June 17, 2015.
Number of inspections: 5
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorThomas Walsh
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR14-00792 INSP-Sprinkler Rough-in6/17/20156/17/20156/18/2015 7:30:59 AMPPART
Rough to cover inspection for 1st floor Bldg. H hard lid areas - see plans for areas inspected.
FIR14-00750 INSP-Sprinkler Rough-in/Hydro6/17/20156/17/20156/18/2015 7:30:29 AMPPASS
Bldg K - Hydrotest of dry pipe system - 200 psi @ 2hours - PASSED
FIR13-00167 INSP-Sprinkler Rough-in/Hydro6/16/20156/17/20156/18/2015 7:30:01 AMPPART
Initial fire pump test, witnessed by Tom Walsh and Tim Frost. Test was conducted at various flows, including no flow, 1000gpm and attempted to conduct 1500 gpm test, but could not flow this portion of the test, due to pressure regulator installed after the pump.
NOTE: Pump test will have to beconducted/ witnessed again when the generator and fire alarm systems interface is completed.
FIR14-00815 INSP-Sprinkler Rough-in6/16/20156/17/20156/17/2015 11:58:22 AMAPART
RTC inspection for 3rd floor corridor for section 1 area of the building. OK to cover pipe in this area.
FIR15-00096 INSP-Sprinkler Rough-in6/16/20156/17/20156/17/2015 11:56:47 AMAPART
RTC unit inspections for insulation for 4th floor west side units, including 421, 422, 423, and 440. This completes the 4th floor west for insulation inspections - OK to cover.