FIR14-00792
| INSP-Sprinkler Rough-in | 6/17/2015 | 6/17/2015 | 6/18/2015 7:30:59 AM | P | PART |
|
|
Rough to cover inspection for 1st floor Bldg. H hard lid areas - see plans for areas inspected.
|
FIR14-00750
| INSP-Sprinkler Rough-in/Hydro | 6/17/2015 | 6/17/2015 | 6/18/2015 7:30:29 AM | P | PASS |
|
|
Bldg K - Hydrotest of dry pipe system - 200 psi @ 2hours - PASSED
|
FIR13-00167
| INSP-Sprinkler Rough-in/Hydro | 6/16/2015 | 6/17/2015 | 6/18/2015 7:30:01 AM | P | PART |
|
|
Initial fire pump test, witnessed by Tom Walsh and Tim Frost. Test was conducted at various flows, including no flow, 1000gpm and attempted to conduct 1500 gpm test, but could not flow this portion of the test, due to pressure regulator installed after the pump. NOTE: Pump test will have to beconducted/ witnessed again when the generator and fire alarm systems interface is completed.
|
FIR14-00815
| INSP-Sprinkler Rough-in | 6/16/2015 | 6/17/2015 | 6/17/2015 11:58:22 AM | A | PART |
|
|
RTC inspection for 3rd floor corridor for section 1 area of the building. OK to cover pipe in this area.
|
FIR15-00096
| INSP-Sprinkler Rough-in | 6/16/2015 | 6/17/2015 | 6/17/2015 11:56:47 AM | A | PART |
|
|
RTC unit inspections for insulation for 4th floor west side units, including 421, 422, 423, and 440. This completes the 4th floor west for insulation inspections - OK to cover.
|