MIS02-00156
| FIR-Final | 6/17/2002 | 6/18/2002 | 6/18/2002 12:00:00 AM | A | FAIL |
|
|
###-#### exiting from sales floor and garage problems; occupancy separation walls aren't one hour as shown on plans; need architect input; left c/n 6/18/2002 11:46:13 AM
|
BLD01-02991
| FIRE-Final Inspection | 6/17/2002 | 6/18/2002 | 6/18/2002 12:00:00 AM | A | PASS |
|
|
RICK ###-####
|
BLD02-00477
| FIRE-Hydro test above ground | 6/17/2002 | 6/18/2002 | 6/18/2002 12:00:00 AM | A | NR |
|
|
###-#### adrian
|
BLD02-00314
| FIRE-Final Inspection | 6/17/2002 | 6/18/2002 | 6/18/2002 12:00:00 AM | A | NR |
|
|
Scheduled by a contractor via Hello! on 06/17/2002 at 17:31:43. Contact: ###-####. GC called and said they aren't ready 6/18/2002 1:22:07 PM
|
BLD02-00545
| FIRE-Sprinkler Rough-in | 6/18/2002 | 6/18/2002 | 6/18/2002 12:00:00 AM | A | PASS |
|
|
Added by Inspector: 409 On 6/18/2002 10:52:43 AM okay to cover
|
FIR02-00093
| INSP-Final Inspection | 6/18/2002 | 6/18/2002 | 6/18/2002 12:00:00 AM | P | PASS |
|
|
Added by Inspector: 409 On 6/18/2002 2:31:05 PM
|
FIR02-00071
| INSP-Final Inspection | 6/18/2002 | 6/18/2002 | 6/18/2002 12:00:00 AM | P | CANC |
|
|
Scheduled by a contractor via Hello! on 06/18/2002 at 07:32:49. Contact: ###-####.
|
FIR02-00212
| INSP-Final Inspection | 6/18/2002 | 6/18/2002 | 6/18/2002 12:00:00 AM | P | PASS |
|
|
fn don -pager- ###-####
|
FIR01-00298
| INSP-Final Inspection | 6/18/2002 | 6/18/2002 | 6/18/2002 12:00:00 AM | P | NR |
|
|
###-####
|
FIR02-00201
| INSP-Final Inspection | 6/18/2002 | 6/18/2002 | 6/18/2002 12:00:00 AM | P | PASS |
|
|
###-####
|
FIR02-00130
| INSP-Sprinkler Rough-in/Hydro | 6/17/2002 | 6/18/2002 | 6/18/2002 12:00:00 AM | P | PART |
|
|
Scheduled by a contractor via Hello! on 06/17/2002 at 16:56:27. Contact: ###-####. met with Mike; will need resubmittals for clean room 6/18/2002 4:52:27 PM
|