FIR01-00124
| INSP-Sprinkler Rough-in/Hydro | 6/18/2002 | 6/19/2002 | 6/19/2002 12:00:00 AM | A | PART |
|
|
OK to cover on the upper floor. other items on the correction list need to be completed 6/19/2002 9:55:33 AM
|
BLD01-00874
| FIRE-Final Inspection | 6/18/2002 | 6/19/2002 | 6/19/2002 12:00:00 AM | A | PASS |
|
|
fire life/safety finaled 6/19/2002 8:23:52 AM
|
BLD02-01222
| FIRE-Final Inspection | 6/18/2002 | 6/19/2002 | 6/19/2002 12:00:00 AM | A | PASS |
|
|
Fire sprinkler and fire life/safety finaled 6/19/2002 11:34:52 AM
|
FIR02-00073
| INSP-Final Inspection | 6/18/2002 | 6/19/2002 | 6/19/2002 12:00:00 AM | P | FAIL |
|
|
all devices need to be tested, heat detectors need to be relocated or the vents blocked, provide 50 ah batteries for the main facp, provide approved hardware on doors, provide updated map 6/19/2002 1:03:15 PM
|
FIR01-00354
| INSP-Alarm Testing | 6/19/2002 | 6/19/2002 | 6/19/2002 12:00:00 AM | P | FAIL |
|
|
provide a knox key box and an updated map 6/19/2002 3:36:52 PM
|
FIR02-00191
| INSP-Final Inspection | 6/19/2002 | 6/19/2002 | 6/19/2002 12:00:00 AM | P | PASS |
|
|
fire sprinkler system finaled 6/19/2002 3:10:29 PM
|