Inspections for the day of: Thursday, June 19, 2003.
Number of inspections: 5
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorSteven Webb
Title 
Phone #794-9491
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD03-00770 BLD-Energy code compliance6/18/20036/19/20036/19/2003 12:00:00 AMAPART
frame corrections and seal package. Seal package done but contractor informed inspector he requested re-inspection on 6/20/03 a.m not this morning. Framing corrections and insulation not ready. Do not cover. 6/19/2003 10:52:03 AM
BLD03-00440 BLD-Footing6/18/20036/19/20036/19/2003 12:00:00 AMAPART
re-inspection. Parameter footings per plan, need interior footings formed and rebar set. Received soils bearing letter from Briggs engineering. Letter stated soils ok. 6/19/2003 9:41:18 AM
BLD03-00773 BLD-Footing6/18/20036/19/20036/19/2003 12:00:00 AMAPART
Scheduled by a contractor via Hello! on 6/18/2003 at 5:31:45 PM. Contact: ###-####. Reviewed retatining walls plans with contractor, more conference instead of inspection, Contractor wants "pass", needs all forms set and rebar in place per plans to get pass. 6/19/2003 9:12:29 AM
ESC03-00242 BMP Violation6/19/20036/19/20036/19/2003 12:00:00 AMAFAIL
Conference with RP--Verbal correction with timeframe by end of day to clean up paint residue from garage apron, sidewalk and street and to remove other pollutants from same. BMP's to be in place. 6/19/2003 9:08:16 AM
ESC03-00445 Site Preparation6/19/20036/19/20036/19/2003 12:00:00 AMAPART
Verbal correction to RP-T. Campbell-Sweep sidewalk and street. Other BMP's per plan. 6/19/2003 9:39:34 AM