BLD08-00633
| FIRE-Final Inspection | 6/19/2008 | 6/19/2008 | 6/19/2008 4:05:21 PM | P | FAIL |
|
|
Mount and tage the fire extinguishers and repair the exit discharge light at the rear exit.
|
FIR08-00288
| INSP-Sprinkler Rough-in | 6/19/2008 | 6/19/2008 | 6/19/2008 4:00:18 PM | P | PASS |
|
|
The tenting appears to be satifactory. I had Lonnie modify tenting in one location. Blow-in insulation can be installed.
|
BLD06-02489
| FIRE-Conference | 6/19/2008 | 6/19/2008 | 6/19/2008 3:53:33 PM | P | DONE |
|
|
The fire proofing of the mechanical supports is complete. The ceiling is these two rooms can be installed covering the sprinkler piping. Insulation has been installed in the eaves as well.
|
FIR08-00094
| INSP-Alarm Testing | 6/19/2008 | 6/19/2008 | 6/19/2008 2:57:45 PM | P | DONE |
|
|
The fire door operated correctly at the junction point of the new ten room addition and the existing facility. This completes the fire alarm in the west two room addition and the ten room addition.
|
BLD07-01845
| FIRE-Final Inspection | 6/18/2008 | 6/19/2008 | 6/19/2008 2:55:45 PM | A | FAIL |
|
|
The inspection today was for the occupancy of the west two room addition and the west ten room addition. The exit discharge light was not installed at the ten room area. I am requiring a exit discharge light at the exit of the two room area per the review comments which reference chapter 10 of the IFC
|
FIR07-00902
| INSP-Sprinkler Rough-in | 6/19/2008 | 6/19/2008 | 6/19/2008 12:15:59 PM | P | PASS |
|
|
The sprinkler piping at the top of the east stair well can be covered. This was the extent of todays inspection. The plans were not marked.
|
BLD07-02455
| FIRE-Final Inspection | 6/19/2008 | 6/19/2008 | 6/19/2008 12:14:33 PM | P | FAIL |
|
|
Remove the thumbturn, provide indicator and sticker as discussed at the west main exit. All other items are passed.
|
FIR07-00874
| INSP-Final Inspection | 6/17/2008 | 6/19/2008 | 6/19/2008 12:13:34 PM | A | PART |
|
|
The fire sprinkler work for the two room west addition and the ten room west addition is complete. 401 canopies have been added at al of the heads that were in conflict with the lights. Jim is to provide 401 canopies for the two pendants that were in the locked closets and change the sidewall heads in the corridor ceiling pockets to quick responce. I will verify this work at the next inspection. Also the sprinkler piping in the connecting corridor, as marked on the approved plans, is ok to cover. This piping has not been connected to the dry system yet and will need to be verified at a later time.
|
FIR08-00377
| INSP-Final Inspection | 6/18/2008 | 6/19/2008 | 6/19/2008 10:40:25 AM | A | PASS |
|
|
Permit finaled
|
FIR08-00372
| INSP-Sprinkler Rough-in | 6/18/2008 | 6/19/2008 | 6/19/2008 10:21:45 AM | A | PASS |
|
|
Sprinkler piping can be covered.
|
FIR08-00202
| FIR-Aging Inspection | 6/19/2008 | 6/19/2008 | 6/19/2008 10:20:44 AM | | NR |
|
|
wip
|
FIR08-00138
| INSP-Final Inspection | 6/18/2008 | 6/19/2008 | 6/19/2008 9:19:38 AM | A | PASS |
|
|
permit finaled
|