BLD00-01176
| BLD-Foundation | 6/1/2000 | 6/2/2000 | 6/2/2000 12:00:00 AM | A | FAIL |
|
|
###-#### Poured w/o inps. remove face paper 6/5/00 10:54:51 AM
|
BLD00-01177
| BLD-Foundation | 6/1/2000 | 6/2/2000 | 6/2/2000 12:00:00 AM | A | FAIL |
|
|
###-#### Poured w/o insp. met w/bldr. onsite. 6/5/00 10:54:39 AM
|
BLD00-00674
| BLD-Framing/Rough-in | 6/1/2000 | 6/2/2000 | 6/2/2000 12:00:00 AM | A | PART |
|
|
###-#### Party wall gyp. ok @ 2nd fl. 6/5/00 10:54:23 AM
|
BLD00-01223
| BLD-Final | 6/1/2000 | 6/2/2000 | 6/2/2000 12:00:00 AM | A | FAIL |
|
|
Barry ###-#### C/N; "cross bracing"- driveway 6/5/00 10:55:20 AM
|
BLD00-01152
| BLD-Framing/Rough-in | 6/1/2000 | 6/2/2000 | 6/2/2000 12:00:00 AM | A | FAIL |
|
|
Scheduled by a contractor via Hello! on 06/01/2000 at 16:30:53. Contact: ###-####. Need elec insp.; C/N: temp. glazing 6/5/00 10:55:07 AM
|
BLD00-00209
| BLD-Framing/Rough-in | 6/1/2000 | 6/2/2000 | 6/2/2000 12:00:00 AM | A | PART |
|
|
Scheduled by a contractor via Hello! on 06/01/2000 at 22:28:52. Contact: ###-####. C/N- complete gyp @ common walls above ceiling- ok to cover except as noted. 6/5/00 10:54:10 AM
|
BLD00-00846
| BLD-Energy code compliance | 6/2/2000 | 6/2/2000 | 6/2/2000 12:00:00 AM | P | PART |
|
|
###-#### reinspection C/N ok- ok to cover (frame ok.) 6/5/00 10:48:13 AM
|
BLD99-02745
| BLD-Framing/Rough-in | 6/2/2000 | 6/2/2000 | 6/2/2000 12:00:00 AM | P | PART |
|
|
Estap ###-#### Foyer area, shear walls ok to cover 6/5/00 10:47:23 AM
|
BLD00-01512
| BLD-Framing/Rough-in | 6/2/2000 | 6/2/2000 | 6/2/2000 12:00:00 AM | P | PART |
|
|
tony ###-#### Bath rm. walls, etc. 6/5/00 10:47:45 AM
|
BLD99-03034
| BLD-Framing/Rough-in | 6/1/2000 | 6/2/2000 | 6/2/2000 12:00:00 AM | P | PART |
|
|
Scheduled by a contractor via Hello! on 06/01/2000 at 17:33:50. Contact: ###-####. Ext. walls only (furring) ok to insul. 6/6/00 11:22:06 AM
|
BLD00-00170
| BLD-Final | 6/1/2000 | 6/2/2000 | 6/2/2000 12:00:00 AM | P | FAIL |
|
|
larry ###-#### Unable to access, recall. 6/5/00 10:47:33 AM
|
BLD99-02055
| BLD-Framing/Rough-in | 6/1/2000 | 6/2/2000 | 6/2/2000 12:00:00 AM | P | PART |
|
|
lower wall outside shear insp Mike ###-#### 1st floor "shear" ok; ok to add gypsum. 6/5/00 10:47:58 AM
|
MEC00-01789
| Rough-in | 6/1/2000 | 6/2/2000 | 6/1/2000 12:00:00 AM | A | CANC |
|
|
Scheduled by a contractor via Hello! on 06/01/2000 at 12:40:09. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on 06/01/2000 at 14:00:29.
|