Inspections for the day of: Thursday, June 2, 2005.
Number of inspections: 10
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD05-00656 FIRE-Final Inspection6/1/20056/2/20056/2/2005 4:04:40 PMPFAIL
Provide exit signs, exit discharge lighting and emergency lights per approved drawing sheet E2.1L, provide suite numbers and TI sprinkler drawings
BLD04-00870 FIRE-Final Inspection6/1/20056/2/20056/2/2005 4:03:33 PMPFAIL
Life safety is ok to final when the shell fire sprinkler permit is finaled
FIR04-00390 INSP-Final Inspection6/1/20056/2/20056/2/2005 2:43:19 PMPFAIL
Need to meet review note #1, need head wrench and forward flush
BLD05-00291 FIRE-Final Inspection6/1/20056/2/20056/2/2005 2:28:34 PMPPART
A temporary occupancy was given until the north exterior door has approved hardware installed. Per contractor hardware to be installed monday.
FIR05-00237 INSP-Final Inspection6/2/20056/2/20056/2/2005 2:11:19 PMPPASS
fire alarm finaled
FIR05-00293 INSP-Final Inspection6/2/20056/2/20056/2/2005 2:08:44 PMPFAIL
Permit can't be finaled until sprinklers are uncovered and ceiling tile is in. Also the main riser needs its annual inspection.
FIR05-00212 INSP-Final Inspection6/2/20056/2/20056/2/2005 12:10:13 PMPFAIL
Provide one piece fittings, need hydro test and anti-freeze signs and annual inspection tag. Need to review all review notes as this turned into just a preliminary inspection.
BLD04-02947 FIRE-Final Inspection6/2/20056/2/20056/2/2005 11:05:59 AMPPASS
Life safety finaled
BLD05-00310 FIRE-Final Inspection6/1/20056/2/20056/2/2005 10:08:27 AMAPASS
Fire life safety finaled. New addition is empty. Can't verify storage.
BLD05-01287 FIRE-Final Inspection6/1/20056/2/20056/2/2005 9:51:57 AMACANC
Duplicate inspection, see previous entry