Inspections for the day of: Tuesday, June 2, 2009.
Number of inspections: 5
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorForrest France
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD08-01555 FIRE-Conference6/2/20096/2/20096/3/2009 8:10:01 AMPDONE
On site conference regarding fire alarm permit work site inspection schedule and related fire sprinkler system interconnections.
BLD08-01640 FIRE-Final Inspection6/2/20096/2/20096/3/2009 8:09:38 AMPPART
On site conference regarding fire alarm permit work site inspection schedule and related fire sprinkler system interconnections.
FIR09-00289 INSP-Final Inspection6/2/20096/2/20096/3/2009 8:06:09 AMPPART
See annotations on plans for alarm devices tested including one pull station at the main FACP and three notification appliances in the west side of the remodel, discussed relocation of existing devices at the east half of the phased work area.
BLD09-00337 FIRE-Final Inspection6/2/20096/2/20096/3/2009 8:02:57 AMPFAIL
Need to post building address numbers, provide signage above the main entry/exit door "door to remain.......", provide a tagged fire extinguisher and post as discussed.
BLD08-02428 FIRE-Final Inspection6/2/20096/2/20096/2/2009 12:54:52 PMPPASS
Building shell life safety inspection completed okay, hardware at the west exit doors to be made compliant prior to occupancy approvals.