FIR10-00659
| INSP-Final Inspection | 6/1/2011 | 6/2/2011 | 6/2/2011 5:18:13 PM | A | PART |
|
|
Final pending coverage at the finished room above the heated garage due to modified 13D requirements and sec. 8.6.5 NFPA13D. Remainder of installation completed satisfactory including flow switch test.
|
FIR11-00224
| INSP-Sprinkler Rough-in | 6/1/2011 | 6/2/2011 | 6/2/2011 5:11:16 PM | A | PART |
|
|
Rough-in okay to cover at units 104 and 204. Head guard installed at SW under stairs while on site.
|
BLD11-01112
| FIRE-Final Inspection | 6/1/2011 | 6/2/2011 | 6/2/2011 5:07:06 PM | A | FAIL |
|
|
Post one fire extinguisher with current certification tag, provide approved hardware at the main entry/exit, post suite address numbers. Refer to permit documents general requirements page items #1,2, and 4 for details.
|