ELE20-01866
| Permanent Service | 6/2/2020 | 6/2/2020 | 6/3/2020 4:56:53 AM | P | PASS |
|
|
Justin Metcalf ###-#### Phone #: ###-#### Inspection requested via web by Samatha Solberg 2 grd rods, intersystem. p/s u/g rec ok
|
ELE20-01846
| Final | 6/1/2020 | 6/2/2020 | 6/2/2020 2:45:17 PM | P | CANC |
|
|
Add on A/C. Tony is our contact @ ###-####. Thank you Phone #: ###-#### Inspection requested via web by Kelly Felin Reshceduled for 6/3 after talking to electrician
|
ELE20-01142
| Final | 6/1/2020 | 6/2/2020 | 6/2/2020 1:52:08 PM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Todd Hall Ok final both units
|
ELE20-01854
| Final | 6/1/2020 | 6/2/2020 | 6/2/2020 1:44:19 PM | A | PASS |
|
|
Replaced electrical service mast - due to wind storm Phone #: ###-#### Inspection requested via web by Kendra Lanham Ok final.
|
ELE20-01855
| Final | 6/1/2020 | 6/2/2020 | 6/2/2020 1:44:05 PM | A | PASS |
|
|
Replaced meter base and mast - due to wind storm Phone #: ###-#### Inspection requested via web by Kendra Lanham Ok final
|
ELE20-01855
| Permanent Service | 6/2/2020 | 6/2/2020 | 6/2/2020 1:43:47 PM | P | PASS |
|
|
Already energized due to tree branch p/s o/h rec ok
|
ELE20-01854
| Permanent Service | 6/2/2020 | 6/2/2020 | 6/2/2020 1:43:09 PM | P | PASS |
|
|
Already energized due to tree branch.. p/s o/h rec ok
|
ELE17-03823
| Final | 6/1/2020 | 6/2/2020 | 6/2/2020 1:38:49 PM | A | CANC |
|
|
Rescheduled from 6/1/20. Needed to get gate code or homeowners contact number. Talked to electrician, rescheduled for 6/3 AM
|
ELE20-00073
| Electrical Rough-In | 6/1/2020 | 6/2/2020 | 6/2/2020 11:55:30 AM | A | PASS |
|
|
Ben Phone #: ###-#### Ok cover remainder of basement
|
ELE20-00710
| Final | 6/2/2020 | 6/2/2020 | 6/2/2020 10:40:43 AM | P | CANC |
|
|
Phone #: ###-#### Inspection requested via web by jamie berg Went through home and checked all recepts and lighting so homeowners have a place to put their furniture. This will be called for a final when completed. Also notified builder that a permit needs pulled on fiberglass pool.
|
ELE20-01862
| Conference | 6/2/2020 | 6/2/2020 | 6/2/2020 10:28:11 AM | P | DONE |
|
|
Discussed location of new panel for ADU to be powered off existing 200a service on house
|
ELE20-01862
| Final | 6/2/2020 | 6/2/2020 | 6/2/2020 10:27:40 AM | P | CANC |
|
|
screened // Ron Phone #: 2###-#### I added a conference, this is not a final.
|
ELE20-01864
| Temporary Service | 6/2/2020 | 6/2/2020 | 6/2/2020 9:42:06 AM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Heath Thomas t/s u/g n ok
|
ELE20-01865
| Electrical Rough-In | 6/2/2020 | 6/2/2020 | 6/2/2020 9:41:30 AM | P | PASS |
|
|
underground, Andy Chambers is contact at ###-####. Phone #: ###-#### Inspection requested via web by Debby Pierce Ok cover grd work N side of school for Parking lot lights
|