ELE20-01543
| Electrical Rough-In | 6/2/2020 | 6/2/2020 | 6/3/2020 2:55:22 PM | A | PASS |
|
|
Please call Chris for inspection of grounding in concrete pad at main gear on exterior of the south side of building. Thanks! Phone #: ###-#### Inspection requested via web by Rafael Castillo...service grounding ok to cover
|
ELE20-01843
| Final | 6/2/2020 | 6/2/2020 | 6/2/2020 2:21:16 PM | P | PASS |
|
|
final for service..labelling complete...exiting sub feed circuit thru attic fixed...sub panels addressed..ok to final
|
ELE20-01839
| Conference | 6/1/2020 | 6/2/2020 | 6/2/2020 12:10:42 PM | P | PASS |
|
|
Rick Phone #: ###-####...discussed wiring of RV circuit to oitside..30A...10/2 romex...stapling..connector for abrasion protection...competent to do work
|
ELE20-01847
| Final | 6/1/2020 | 6/2/2020 | 6/2/2020 11:22:47 AM | P | PASS |
|
|
Disconnect needs replaced for A/C adding service outlet. Thank you Phone #: ###-#### Inspection requested via web by Kelly Felin...ok to final
|
ELE20-01243
| Final | 6/1/2020 | 6/2/2020 | 6/2/2020 11:13:51 AM | P | PASS |
|
|
The owner lives in 3953 if you need access. Phone #: ###-#### Inspection requested via web by Jason Scott...ok to final
|
ELE20-01242
| Final | 6/1/2020 | 6/2/2020 | 6/2/2020 11:13:28 AM | P | PASS |
|
|
the owner lives in 3953 if you need access. Phone #: ###-#### Inspection requested via web by Jason Scott...ok to final
|
ELE20-01783
| Final | 6/1/2020 | 6/2/2020 | 6/2/2020 9:51:11 AM | A | PASS |
|
|
Shawn *screened* Phone #: ###-####... corrections made...ok to final
|
ELE20-01859
| Final | 6/1/2020 | 6/2/2020 | 6/2/2020 9:24:01 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Kim Galvin...ok to barry conduit...job complete...ok to final
|
ELE20-01836
| Permanent Service | 6/1/2020 | 6/2/2020 | 6/2/2020 8:28:38 AM | A | PASS |
|
|
screened - Service only - Milenko Phone #: ###-####... p/s o/h ok connect to new location
|