Inspections for the day of: Wednesday, June 20, 2001.
Number of inspections: 17
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorRuss Owen
TitleBLD-COM/RES INSPECTOR
Phone #794-9473
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
MEC01-01651 Rough-in6/19/20016/20/20016/20/2001 12:00:00 AMAFAIL
Scheduled by a contractor via Hello! on 06/19/2001 at 10:58:34. Contact: ###-####. seal return air, plumbing pipe penetrations and holes in the floor joist . 1/20/2002 2:13:20 PM
MEC01-01651 Pressure Test6/19/20016/20/20016/20/2001 12:00:00 AMAPASS
Scheduled by a contractor via Hello! on 06/19/2001 at 10:58:48. Contact: ###-####.
MEC00-04134 Pressure Test6/19/20016/20/20016/20/2001 12:00:00 AMAPASS
Scheduled by a contractor via Hello! on 06/19/2001 at 12:04:08. Contact: ###-####. pool heater 1/20/2002 11:16:51 AM
BLD01-01594 BLD-Footing6/19/20016/20/20016/20/2001 12:00:00 AMAPASS
###-####
MEC01-01799 Final6/19/20016/20/20016/20/2001 12:00:00 AMAPASS
###-####
MEC01-01339 Final6/19/20016/20/20016/20/2001 12:00:00 AMAPASS
Scheduled by a contractor via Hello! on 06/19/2001 at 16:00:26. Contact: ###-####.
BLD01-01566 BLD-Footing6/19/20016/20/20016/20/2001 12:00:00 AMAPASS
Scheduled by a contractor via Hello! on 06/19/2001 at 17:52:39. Contact: .
BLD00-03660 BLD-Final6/19/20016/20/20016/20/2001 12:00:00 AMAPASS
Scheduled by a contractor via Hello! on 06/19/2001 at 18:32:48. Contact: ###-####.
BLD01-01594 BLD-Framing/Rough-in6/19/20016/20/20016/20/2001 12:00:00 AMACANC
###-####
BLD01-00588 BLD-Footing6/19/20016/20/20016/20/2001 12:00:00 AMPFAIL
###-#### verbal c/n with contractor from wright brothers, front wall req 2 bars top and bottom also 6 in wider footing at the front entry also inst shear footings require a 6 in raise above the slab,also clearance to earth at several locations, not this is a mono pour for footing and slab. 1/20/2002 5:18:37 PM
BLD01-01333 BLD-Framing/Rough-in6/20/20016/20/20016/20/2001 12:00:00 AMPFAIL
SHEAR NAIL ###-#### c/n posted. 1/20/2002 3:34:17 PM
BLD01-01182 BLD-Framing/Rough-in6/20/20016/20/20016/20/2001 12:00:00 AMPPART
Scheduled by a contractor via Hello! on 06/20/2001 at 08:55:01. Contact: ###-####. NO plans at the syte roof trusses only ok roof truss system ,c/n to provide plans. 1/20/2002 4:23:58 PM
MEC01-01793 Pressure Test6/20/20016/20/20016/20/2001 12:00:00 AMPPASS
reinspection Dean ###-#### please check fixture count for me
BLD00-02817 BLD-Energy code compliance6/20/20016/20/20016/20/2001 12:00:00 AMPCANC
John ###-####
BLD01-01566 BLD-Footing1/20/20026/20/20016/20/2001 12:00:00 AMPPART
Added by Inspector: 407 On 1/20/2002 3:19:06 PM had to add this in ,first entry incorrect, footings poured no plans on site.
BLD01-00999 BLD-Wall cover6/19/20016/20/20016/20/2001 12:00:00 AMPPASS
Scheduled by a contractor via Hello! on 06/19/2001 at 17:28:08. Contact: ###-####.
BLD01-00202 BLD-Final6/19/20016/20/20016/20/2001 12:00:00 AMPFAIL
###-#### c/n posted. 1/20/2002 6:54:15 PM