ELE01-02078
| Electrical Rough-In | 6/21/2001 | 6/22/2001 | 6/22/2001 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 06/21/2001 at 11:33:48. Contact: .
|
ELE01-01988
| Electrical Rough-In | 6/21/2001 | 6/22/2001 | 6/22/2001 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 06/21/2001 at 12:30:09. Contact: ###-####.
|
ELE01-02074
| Electrical Rough-In | 6/21/2001 | 6/22/2001 | 6/22/2001 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 06/21/2001 at 13:52:54. Contact: ###-####.
|
ELE01-02035
| Temporary Service | 6/21/2001 | 6/22/2001 | 6/22/2001 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 06/21/2001 at 16:20:49. Contact: ###-####. T/S U/G OK 6/22/2001 10:54:37 AM
|
ELE01-01650
| Rough-In Permanent Service | 6/22/2001 | 6/22/2001 | 6/22/2001 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 06/22/2001 at 07:11:16. Contact: ###-####. Ok for power on meter pack 6/22/2001 9:43:18 AM
|
ELE01-02038
| Electrical Rough-In | 6/22/2001 | 6/22/2001 | 6/22/2001 12:00:00 AM | P | PART |
|
|
r/i for interior walls partial warren ###-####
|
ELE01-02052
| Final | 6/22/2001 | 6/22/2001 | 6/22/2001 12:00:00 AM | P | NR |
|
|
Richard ###-#### R/I Only ok 6/22/2001 3:44:13 PM
|
ELE01-01745
| Final | 6/22/2001 | 6/22/2001 | 6/22/2001 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 06/22/2001 at 10:03:21. Contact: ###-####.
|
ELE01-01383
| Permanent Service | 6/22/2001 | 6/22/2001 | 6/22/2001 12:00:00 AM | P | PASS |
|
|
Duane ###-#### Bldg #4 P/S U/G N Ok 6/22/2001 12:43:23 PM
|
ELE01-01814
| Electrical Rough-In | 6/22/2001 | 6/22/2001 | 6/22/2001 12:00:00 AM | P | PASS |
|
|
Added by Inspector: 336 On 6/22/2001 12:42:32 PM
|