FIR07-00971
| INSP-Final Inspection | 6/19/2009 | 6/22/2009 | 6/22/2009 5:10:14 PM | P | PART |
|
|
Items needed for final include adjustment at the PIV tamper switch, program door holds at two locations to release on general alarm conditon, elevator recall functions did not operate correctly. Remainder of installation passed field testing.
|
FIR09-00080
| FIR-Aging Inspection | 6/22/2009 | 6/22/2009 | 6/22/2009 5:07:42 PM | | DONE |
|
|
Pending site inspection request for work completed.
|
FIR08-00699
| INSP-Sprinkler Rough-in | 6/22/2009 | 6/22/2009 | 6/22/2009 5:06:42 PM | P | PART |
|
|
Initialed and dated plans where grid ceiling areas are approved for cover including the library and administration offices.
|
BLD09-00326
| FIRE-Final Inspection | 6/19/2009 | 6/22/2009 | 6/22/2009 5:05:39 PM | A | PASS |
|
|
Fire life safety is satisfactory when deadbolts at two existing exterior warehouse doors are removed and one EM light in the new stairway is repaired-to be verified for completion prior to structural final as agreed. Self contained type one kitchen appliance is as indicated on plans is not installed.
|
FIR09-00272
| INSP-Final Inspection | 6/22/2009 | 6/22/2009 | 6/22/2009 5:02:37 PM | A | PASS |
|
|
Corrections completed, fire sprinkler permit okayed for final. Future coolers as shown on plans are not installed at this time.
|
FIR09-00264
| INSP-Sprinkler Rough-in/Hydro | 6/19/2009 | 6/22/2009 | 6/22/2009 5:00:46 PM | A | PART |
|
|
Begin 24 hr. air testing for the new dry system at 40.5 psig @ 10:00.
|
FIR08-00786
| INSP-Final Inspection | 6/22/2009 | 6/22/2009 | 6/22/2009 4:57:42 PM | A | PASS |
|
|
Record drawings accepted, fire alarm permit okayed for final status.
|