Inspections for the day of: Monday, June 22, 2015.
Number of inspections: 4
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorThomas Walsh
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR14-00727 INSP-Final Inspection6/22/20156/22/20156/22/2015 11:28:32 AMPPASS
Final Inspection - PASSED
FIR15-00096 INSP-Sprinkler Rough-in/Hydro6/19/20156/22/20156/22/2015 11:01:29 AMAPART
Insulation (tenting) inspection for 5th floor wet pipe system - south side corridor from unit 527 to south stair lobby, also inuts 521, 522, 523, 524 and 525. All inspected OK after a few field adjustments were made to provide adequate protection of CPVC pipe.
FIR15-00096 INSP-Sprinkler Rough-in6/19/20156/22/20156/22/2015 10:58:10 AMAPASS
Reinspection of 5th floor units 517 and 518 to reinspect for dry pipe sprinkler obstructions. The changes inspected OK, and this completes the rough inspection for the south side dry pipe system.
NOTE: 24 hour air test and hydrotest of this system will be scheduled at a future date.
FIR14-00727 INSP-Sprinkler Rough-in/Hydro6/22/20156/22/20156/22/2015 9:59:35 AMPPASS
Retested one HVAC unit for SD shutdown for the Bldg. D commons area. The unit shutdown when tested. That was the last test needed for final sign-off.
PASSED and Finaled.