FIR14-00727
| INSP-Final Inspection | 6/22/2015 | 6/22/2015 | 6/22/2015 11:28:32 AM | P | PASS |
|
|
Final Inspection - PASSED
|
FIR15-00096
| INSP-Sprinkler Rough-in/Hydro | 6/19/2015 | 6/22/2015 | 6/22/2015 11:01:29 AM | A | PART |
|
|
Insulation (tenting) inspection for 5th floor wet pipe system - south side corridor from unit 527 to south stair lobby, also inuts 521, 522, 523, 524 and 525. All inspected OK after a few field adjustments were made to provide adequate protection of CPVC pipe.
|
FIR15-00096
| INSP-Sprinkler Rough-in | 6/19/2015 | 6/22/2015 | 6/22/2015 10:58:10 AM | A | PASS |
|
|
Reinspection of 5th floor units 517 and 518 to reinspect for dry pipe sprinkler obstructions. The changes inspected OK, and this completes the rough inspection for the south side dry pipe system. NOTE: 24 hour air test and hydrotest of this system will be scheduled at a future date.
|
FIR14-00727
| INSP-Sprinkler Rough-in/Hydro | 6/22/2015 | 6/22/2015 | 6/22/2015 9:59:35 AM | P | PASS |
|
|
Retested one HVAC unit for SD shutdown for the Bldg. D commons area. The unit shutdown when tested. That was the last test needed for final sign-off. PASSED and Finaled.
|