Inspections for the day of: Wednesday, June 22, 2016.
Number of inspections: 9
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorKatie Marron
TitleFIRE INSPECTOR
Phone #395-7809
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
NAF15-00041 INSP-Sprinkler Rough-in6/21/20166/22/20166/22/2016 2:19:07 PMPPASS
Remainder of UDG OK to cover. Observed thrust blocks being poured.
NAF15-00039 INSP-Sprinkler Rough-in/Hydro6/21/20166/22/20166/22/2016 2:18:27 PMPPASS
Hydro static test completed satisfactory. Only flush remains.
NAF15-00038 INSP-Sprinkler Rough-in/Hydro6/21/20166/22/20166/22/2016 2:18:05 PMPPASS
Hydro static test completed satisfactory. Only flush remains.
NAF15-00038 INSP-Supply line flush6/21/20166/22/20166/22/2016 1:17:20 PMPCANC
Flush after hydro Phone #: ###-#### >> Inspection requested via web by Sam Ball Inspection cancelled from web by: Sam Ball
NAF15-00039 INSP-Supply line flush6/21/20166/22/20166/22/2016 1:16:45 PMPCANC
Flush after hydro Phone #: ###-#### >> Inspection requested via web by Sam Ball Inspection cancelled from web by: Sam Ball
FIR16-00185 INSP-Final Inspection6/21/20166/22/20166/22/2016 10:34:21 AMAFAIL
The smoke detectors and strobes on 2nd floor verified "OK". Duct detectors did not shut down fan. Following items needed:
- Updated map of devices at panel
- Junction box cover by relays in mech room
- Retest of duct detectors to verify fan shut down
FIR16-00374 INSP-Final Inspection6/21/20166/22/20166/22/2016 9:30:33 AMAPASS
Scope of work complete. Permit Finaled.
BLD15-04544 FIRE-Conference6/22/20166/22/20166/22/2016 12:00:00 AMADONE
Fire Sprinkler Permit is not linked to BLD. Ensure FIR16-00084 is signed off before finaling
GCB15-00001 FIRE-Final Inspection6/22/20166/22/20166/22/2016 12:00:00 AMAPASS
Life Safety Pass.