ELE18-02047
| Conference | 6/20/2018 | 6/22/2018 | 6/22/2018 4:32:15 PM | P | PASS |
|
|
Please call ahead for access - Charles Phone #: ###-####...discussed hooking up HR to microwave in panel...coonector and breaker placement
|
ELE18-02047
| Electrical Rough-In | 6/22/2018 | 6/22/2018 | 6/22/2018 4:28:00 PM | P | PASS |
|
|
Please call ahead for access - Charles Phone #: ###-####...rough in kitchen ok to cover...can light wires fished in
|
ELE12-02903
| ELE-Aging Inspection | 6/22/2018 | 6/22/2018 | 6/22/2018 2:28:40 PM | | PASS |
|
|
permit expired
|
ELE12-02903
| DOC - Permit Expired | 6/22/2018 | 6/22/2018 | 6/22/2018 2:28:20 PM | P | PASS |
|
|
made multiple attempts to final
|
ELE18-02171
| Final | 6/22/2018 | 6/22/2018 | 6/22/2018 2:20:10 PM | P | PASS |
|
|
Pls contact Mike (Foreman) @ ###-#### or Barry (Electrician) @ ###-#### one hr prior or if you have any questions. Thank you. Inspection requested via web by Rob Maes..added 2 panels to existing equipment...no upsizing of wire or OCPD neded
|
ELE18-02171
| Electrical Rough-In | 6/18/2018 | 6/22/2018 | 6/22/2018 2:19:15 PM | P | PASS |
|
|
Pls contact Mike (Foreman) @ ###-#### or Barry (Electrician) @ ###-#### one hr prior or if you have any questions. Thank you. Inspection requested via web by Rob Maes...UL listed equipment verified
|
ELE18-02103
| Final | 6/21/2018 | 6/22/2018 | 6/22/2018 1:49:31 PM | P | CANC |
|
|
Ian Phone #: ###-####...not ready at this time...changed to rough in inspection
|
ELE18-02103
| Electrical Rough-In | 6/22/2018 | 6/22/2018 | 6/22/2018 1:48:48 PM | P | PASS |
|
|
Ian Phone #: ###-####...EQ potential bonding and rough of shed for pool equipment...discussed 3' needed clearance infront of pool sub panel...will move...also wire from house to pool shed needs to be #6 THHN...romex not aloud for use outside or underground
|
ELE18-02202
| Permanent Service | 6/22/2018 | 6/22/2018 | 6/22/2018 1:12:32 PM | P | CANC |
|
|
Kenny is the site contact. Thank you Phone #: ###-#### Inspection requested via web by Stacie Tasker...wrong type of inspection...changed to rough and final
|
ELE18-02202
| Final | 6/22/2018 | 6/22/2018 | 6/22/2018 1:11:58 PM | P | PASS |
|
|
Kenny is the site contact. Thank you Phone #: ###-#### Inspection requested via web by Stacie Tasker...job complete...labelling and OCPD correct.. ok to final
|
ELE18-02202
| Electrical Rough-In | 6/22/2018 | 6/22/2018 | 6/22/2018 1:11:05 PM | P | PASS |
|
|
Kenny is the site contact. Thank you Phone #: ###-#### Inspection requested via web by Stacie Tasker...piping to new sub panel off existing panel and circuits to 2 car charger stations...ok
|
ELE18-02118
| Permanent Service | 6/22/2018 | 6/22/2018 | 6/22/2018 11:51:14 AM | P | PASS |
|
|
Von is the contact Phone #: ###-#### Inspection requested via web by Buster Bowen...p/s u/g new ok
|
ELE17-03003
| Final | 6/21/2018 | 6/22/2018 | 6/22/2018 11:04:53 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by cris flores...job complete..ok to final
|
ELE18-01891
| Final | 6/21/2018 | 6/22/2018 | 6/22/2018 10:17:12 AM | A | PASS |
|
|
Pls contact Brad (Foreman) @ ###-#### or Preston (Electrician) ###-#### one hr prior or if you have any questions. Thank you. Inspection requested via web by Rob Maes...labelling, disconnect, and OCPD ok
|
ELE17-02649
| Electrical Rough-In | 6/21/2018 | 6/22/2018 | 6/22/2018 10:02:34 AM | A | PASS |
|
|
Ceiling inspection - contact is Andy Chambers Phone #: ###-#### Inspection requested via web by Scott Campbell...grid ok...as marked on plans
|
ELE18-01451
| Electrical Rough-In | 6/21/2018 | 6/22/2018 | 6/22/2018 8:57:09 AM | A | PASS |
|
|
inspect light nitch potting before filling with water Phone #: ###-#### Inspection requested via web by ron spen cer,,,potting compound for lights and bonding for slide
|
ELE18-01886
| Electrical Rough-In | 6/21/2018 | 6/22/2018 | 6/22/2018 8:23:09 AM | A | PASS |
|
|
Ceiling cover Phone #: ###-#### Inspection requested via web by David Feller...grid ok to cover
|