FIR20-00257
| INSP-Sprinkler Rough-in | 6/22/2020 | 6/22/2020 | 6/22/2020 3:53:15 PM | P | PASS |
|
|
Previously noted item has been corrected, rough in inspection complete.
Tony Cetani is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
FIR20-00271
| INSP-Sprinkler Rough-in | 6/22/2020 | 6/22/2020 | 6/22/2020 3:53:15 PM | P | PASS |
|
|
Rough to cover inspection for remaining area of work complete, approved for cover.
screened // Rick Phone #: ###-####
|
FIR20-00047
| INSP-Sprinkler Rough-in | 6/19/2020 | 6/22/2020 | 6/22/2020 10:16:15 AM | A | FAIL |
|
|
Upright coverage in Board Room around partition wall is overspaved, partition wall framing goes all the wat too deck, correct uprigh coverage issue. Office B131 has upright overspacing issues, correct spacing to be compliant with NFPA13. Fire sprinkler head in east main entry is painted, replace painted head. Pendant heads in northeast main entry area with be hit by cabinet dooes in current locaiton, sprinkler heads in front of cabinets will need to be relocated, inspection stopped, a full rough in with exception to hardlids will need to be completed.
Jim Baker is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
FIR20-00063
| INSP-Final Inspection | 6/22/2020 | 6/22/2020 | 6/22/2020 9:40:09 AM | A | PASS |
|
|
Previously noted items have been corrected, final fire sprinkler inspection is complete.
Call James before heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
FIR20-00075
| INSP-Final Inspection | 6/22/2020 | 6/22/2020 | 6/22/2020 9:39:28 AM | A | PASS |
|
|
Final fire sprinkler inspection is complete, irrigation shut-down on flow switch activation witnessed during water flow.
Call James before heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|