Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR08-00117 INSP-Final Inspection6/23/20086/23/20086/26/2008 9:48:31 AMPNH
Larren Phone #: ###-####
FIR08-00052 INSP-Final Inspection6/23/20086/23/20086/23/2008 4:51:08 PMPPASS
Fire sprinkler permit finaled.
FIR08-00121 INSP-Final Inspection6/23/20086/23/20086/23/2008 4:49:31 PMPFAIL
See five item correction notice for defficient items.
FIR08-00329 INSP-Sprinkler Rough-in6/23/20086/23/20086/23/2008 4:48:07 PMPNR
Tenant work is not yet completed for rough-in inspection.
FIR08-00328 INSP-Sprinkler Rough-in6/23/20086/23/20086/23/2008 4:47:14 PMPNR
mike Phone #: ###-####
BLD08-00655 FIRE-Final Inspection6/23/20086/23/20086/23/2008 1:20:42 PMPPASS
Repairs made as per Troy Cobbley's last inspection.KR
BLD08-01035 BLD-Conference6/23/20086/23/20086/23/2008 12:59:00 PMPPASS
Exit signs did not work when test button was pushed, Owners will repair. Tony Young will verify that the exit lights work during his inspection. All other life safety inspection completed. KR
FIR08-00430 INSP-Final Inspection6/20/20086/23/20086/23/2008 12:48:39 PMPPASS
Sprinkler quick permit finaled. KR
FIR07-00863 INSP-Sprinkler Rough-in6/23/20086/23/20086/23/2008 12:48:24 PMPPART
Inspection for overhead antifreeze and wet systems at the second floor level completed acceptable, as-built plans for field changes at the antifreeze system okayed, see dated initials on plans. NOTE: cover approval pending inspection for tenting when finished.
FIR08-00327 INSP-Sprinkler Rough-in6/23/20086/23/20086/23/2008 12:43:34 PMPPART
See city stamped plan set for location of one overspaced head at the entry vestibule to be relocated, tenting is not completed for wet system cold cavity protection at this time, remainder of OH install at the tenant area is satisfactory although not yet approved for cover.
FIR08-00418 INSP-Sprinkler Rough-in/Hydro6/23/20086/23/20086/23/2008 12:38:08 PMANR
Jim Phone #: ###-####
BLD07-01932 FIRE-Conference6/23/20086/23/20086/23/2008 12:35:47 PMPDONE
Done in conjunction with project related fire alarm testing. Discussed job finish schedule, elevator upgrade completion date, access controled door hardware, noted one fire extinguisher overdue annual certification.
FIR08-00047 INSP-Alarm Testing6/23/20086/23/20086/23/2008 10:58:15 AMAPART
See correction notice for list of items in need of revision.
BLD07-01188 FIRE-Final Inspection6/23/20086/23/20086/23/2008 10:55:12 AMPNR
Fire life safety final cannot be completed until project related alarm and sprinkler permits are finaled-see details listed in FIR permit activities for specific items remaining.
FIR08-00121 INSP-Alarm Testing6/20/20086/23/20086/23/2008 10:51:44 AMAFAIL
Provide map at the FACP, missing signage at the door to the fire alarm panel room, provide visual notification for the women's fitting room vestibule per plan review annotations, door mag locks at the south and north exits are not installed at this time for functional testing of interconnection to the fire alarm system, noted RTU #3 duct detector is not operational at the factory installed supply side (return side is okay), addresses at RTU # 1 amendend while on site, will sign record of completion forms when c/n items are finished, remainder of fire alarm work test passed including signal monitoring.
FIR07-00997 INSP-Final Inspection6/20/20086/23/20086/23/2008 10:42:04 AMAFAIL
Provide certification for the RPB, relocate the automatic ball drip for the fire dept. connection, provide missing "911" sign at the outside bell, provide pitot and playpipe for functional forward flow testing per review notes, need to attatch calc stickers, riser signage, state tag etc.
BLD08-01265 FIRE-Final Inspection6/20/20086/23/20086/20/2008 12:59:37 PMACANC
josh Phone #: ###-#### Inspection cancelled from web by: Alexandra Rahn