Inspections for the day of: Monday, June 23, 2014.
Number of inspections: 5
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD14-00402 FIRE-Final Inspection6/20/20146/23/20146/23/2014 3:30:49 PMPFAIL
Need fire lane signs as per the fire dept review comments.
FIR13-00697 INSP-Sprinkler Rough-in6/23/20146/23/20146/23/2014 3:28:16 PMPPASS
Lab and Equipment rooms sprinklers are complete. Piping in lobby area ok to cover. See city approved plans.
FIR13-00460 INSP-Sprinkler Rough-in/Hydro6/23/20146/23/20146/23/2014 1:56:01 PMPPASS
Underground hydro test passed
FIR14-00248 INSP-Sprinkler Rough-in6/23/20146/23/20146/23/2014 1:55:25 PMPPART
24 hour air test started at 12:30 with 44 psi
BLD14-00484 FIRE-Final Inspection6/23/20146/23/20146/23/2014 8:32:51 AMPPART
Life safety in phase 2 and 3 passed.