FIR15-00096
| INSP-Sprinkler Rough-in | 6/22/2015 | 6/23/2015 | 6/23/2015 2:38:17 PM | P | PART |
|
|
Tenting (insulation) inspection for 5th floor wet system, including units 526, 527, 528, and 529 on the west side, and units 519, and 520 on the east side. Also 5th floor corrdor on the southwest side to unit 529. OK to cover pipe in these areas.
|
BLD13-03389
| FIRE-Final Inspection | 6/23/2015 | 6/23/2015 | 6/23/2015 2:15:27 PM | P | PASS |
|
|
Final sign off of grading permit by Fire. FS U/G permit also signed off.
|
FIR14-00815
| INSP-Sprinkler Rough-in | 6/22/2015 | 6/23/2015 | 6/23/2015 2:09:03 PM | P | PART |
|
|
RTC inspection for 2nd and 3rd fllor corridors for section 2 of the bldg. PASSED - OK to cover.
|
FIR14-00191
| INSP-Sprinkler Rough-in/Hydro | 6/23/2015 | 6/23/2015 | 6/23/2015 8:45:59 AM | P | PASS |
|
|
FS U/G supply OK to final, per Scott Arellano's email, dated 6/23/15. Hydrotest and flush of U/G supply witnessed by this office, but not documented in permit file.
|